PE Exam Reference Quiz

PE Exam Reference Quiz

University

92 Qs

quiz-placeholder

Similar activities

FALTA REDES EXAMEN CORREO

FALTA REDES EXAMEN CORREO

1st Grade - University

93 Qs

Algebra 1 Semester 1 Final Exam Review

Algebra 1 Semester 1 Final Exam Review

9th Grade - University

90 Qs

ITB Final Review 2020

ITB Final Review 2020

University

94 Qs

GNED 03 MATH REVIEW

GNED 03 MATH REVIEW

University

90 Qs

Ancient Greece - Part 2

Ancient Greece - Part 2

7th Grade - University

90 Qs

Combinatorics and probability

Combinatorics and probability

11th Grade - University

93 Qs

Chapter 2 (Transformations)

Chapter 2 (Transformations)

8th Grade - University

89 Qs

mEEth 2019

mEEth 2019

University

94 Qs

PE Exam Reference Quiz

PE Exam Reference Quiz

Assessment

Quiz

Mathematics

University

Practice Problem

Easy

Created by

rey moralde

Used 1+ times

FREE Resource

92 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

For any proposed bridge site, the topographic and river surveys should be extended from the centerline of the bridge at least

100 to 200 upstream only

100 to 200 downstream only

100 to 200 upstream and downstream

300 m upstream and downstream

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the simplest type of superstructure of a concrete bridge with a limited span of 8 meters?

Reinforced concrete slab

Concrete plank deck

Girder and slab superstructure

Beam or Plank Bridge

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of these is not classified as a type of caisson foundation?

Pneumatic foundation

Box caisson

Open caisson

Hydraulic caisson

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following documents is not necessary at the project site?

Bill of quantities

Plans

General specification

Feasibility study

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An asphalt cement can be a good bituminous binder material for item

306

308

310

311

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The following reasons may cause the granting of contract time extension with the exception of one:

Exceptionally adverse climate conditions

Excusable failure of contractor to provide equipment and man power

Causes beyond the control of contractor

Causes of which government is not directly responsible

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the allowable variance from the original unit price, so that a contract will be entitled to contract price escalation?

Less than 2 %

Less than 5 %

More than 5 %

Less than 3 %

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?