construction

construction

University

8 Qs

quiz-placeholder

Similar activities

UNIT 109 PPT 3 KNOWLEDGE CHECK AND STARTER.

UNIT 109 PPT 3 KNOWLEDGE CHECK AND STARTER.

12th Grade - University

11 Qs

FBC: Building Finishes

FBC: Building Finishes

University

12 Qs

Post-Occupancy Review and In Use - OSHA

Post-Occupancy Review and In Use - OSHA

University

10 Qs

110 Contract Quiz

110 Contract Quiz

University

10 Qs

Quiz on Legal & Statutory Requirements in Construction

Quiz on Legal & Statutory Requirements in Construction

University

9 Qs

Construction Management Principles

Construction Management Principles

University

7 Qs

Project Planning

Project Planning

University

10 Qs

Planer Safety Test - Test #2

Planer Safety Test - Test #2

9th Grade - University

13 Qs

construction

construction

Assessment

Quiz

Construction

University

Medium

Created by

YanXin Ooi

Used 1+ times

FREE Resource

8 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Which of the following is NOT a government incentive for reviving abandoned construction projects?

Tax Incentives for Rescuing Developers

Free land grants for developers of abandoned projects

Stamp duty exemption for buyers of abandoned housing projects extended

Special Financing Guarantee

2.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

When does the business of a construction contract commence?

i) The date the contract is secured, a letter of award is offered, or possession of the site is obtained

ii) The commencement of an activity that is part of a series of activities in the construction contract business

iii) Any other date the Director General of Inland Revenue considers appropriate and reasonable

i and ii

i and iii

ii and iii

All of above

3.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

What method is used to recognize income from construction contracts based on the progress of the work? 

Cash basis method

Percentage of completion method

Completed contract method

Cost recovery method

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A construction contract has a total price of RM 1,200,000. The costs incurred so far are RM 600,000, and the estimated total cost is RM 1,000,000. If the estimated profit is RM 200,000, what is the percentage of completion?

50%

75%

60%

80%

5.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

What is meant by 'Defect Liability'?

Compensation for late delivery of the project

Repair costs incurred after project completion

Additional tax after the project is completed

Cost of construction materials

6.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

For completion contracts, the action of the ‘excess shall be taken as gross income for the final year basis’ is adopted in which of the following situations?

Actual GP = Estimated GP

  1. Actual GP > Estimated GP

  1. Actual GP < Estimated GP

Actual Loss

7.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Which of the following statements about costs incurred after project completion is TRUE according to PR 2/2009?

Defect liability costs are only deductible if there is sufficient income from the contract in the same year

Late Ascertained Damages (LAD) can only be claimed in the year the contract is completed.

If there is insufficient income and no election is made, defect liability can be deducted against income from other contracts or other sources.

  1. Irrevocable election allows deduction of defect liability against the gross income of all contracts, regardless of period.

8.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

If A= Progress billings, B= Total price and C= Estimated profit

    What is the correct equation for PERCENTAGE OF COMPLETION?

(A/B) x C

(B-A) x C

(A/C) x B

(A-B) x C