During project execution, the use of a check-in/check-out technology that is used on the project to coordinate the deliverables has become unstable, which puts the whole project at risk of failure. Your communications management plan must be updated to address this issue. You want to know what is the established procedure. What should you do next?

pre-test pmp (61)

Quiz
•
others
•
Professional Development
•
Medium
Training eNetwoQ ServIT Indonesia
Used 2+ times
FREE Resource
5 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Consult the communications management plan
Consult the risk register
Consult the stakeholder engagement plan
Submit a change request to replace the technology
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are the project manager in an organization having multiple ongoing projects and information technology. As you are integrating the information from different projects, you find that the stakeholder engagement assessment matrix for your project is not accurate. You discover that the communication style assessment was not performed, leading to some stakeholders being overlooked. After researching the issue, you decide that the missing communication style assessment needs to be completed. What might be your next step?
Perform a communication style assessment
Provide technical training for the managing department
Review the stakeholder engagement assessment matrix
Update the stakeholder engagement management plan
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are leading a project with a small and cordial project staff and rarely deal with any disputes. An argument between two project team members over a minor form template issue in a design phase escalates, threatening the team's focus and engagement. You realize that resolving the conflict would delay the project. What is your best course of action?
Tell the team members to figure it out for themselves
Look for an interim trial that would completely avoid any further clashes
Reassign the important format task to avoid any further clashes
Select the report format that you think is the best and make the decision.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are in the finalization stage of a project that aims to design and then maintain the new chassis for an automated production line for a returning client. In the project charter, the service level agreement (SLA) is the central of a breakdown. What should you do to be the first to reference it?
Do change scope requirements as they are just available during project initiation
Refer to the procurement management plan
Review any emails or other correspondence with the client
Check the service level agreement with the client
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are planning a kick-off meeting for your new project. The meeting will communicate the start of the project, key milestones, and other relevant information. Which of the following describes the objective of this meeting?
Inform and engage stakeholders and gain commitment
Manage threats and opportunities throughout the project
Ensure that the project is completed on schedule and budget
Secure resources required to complete project deliverables
Similar Resources on Wayground
10 questions
Heat Pump Quiz

Quiz
•
Professional Development
10 questions
ASSESSMENT GLOBAL MINDSET

Quiz
•
Professional Development
5 questions
pre-test pmp (61)

Quiz
•
Professional Development
7 questions
Construction Site Safety Quiz

Quiz
•
Professional Development
10 questions
MarkFest 2022-2023

Quiz
•
Professional Development
8 questions
Write the gerund

Quiz
•
Professional Development
5 questions
SMMM

Quiz
•
Professional Development
9 questions
English Grammar Quiz

Quiz
•
Professional Development
Popular Resources on Wayground
25 questions
Equations of Circles

Quiz
•
10th - 11th Grade
30 questions
Week 5 Memory Builder 1 (Multiplication and Division Facts)

Quiz
•
9th Grade
33 questions
Unit 3 Summative - Summer School: Immune System

Quiz
•
10th Grade
10 questions
Writing and Identifying Ratios Practice

Quiz
•
5th - 6th Grade
36 questions
Prime and Composite Numbers

Quiz
•
5th Grade
14 questions
Exterior and Interior angles of Polygons

Quiz
•
8th Grade
37 questions
Camp Re-cap Week 1 (no regression)

Quiz
•
9th - 12th Grade
46 questions
Biology Semester 1 Review

Quiz
•
10th Grade