Quiz time

Quiz time

University

30 Qs

quiz-placeholder

Similar activities

Planning

Planning

11th Grade - University

25 Qs

UNIT 5 M6 EIC UNIT TEST

UNIT 5 M6 EIC UNIT TEST

12th Grade - University

25 Qs

Software Measurement 26-50

Software Measurement 26-50

University

25 Qs

OOSE

OOSE

University

25 Qs

Timebound

Timebound

University

25 Qs

Time Lines

Time Lines

6th Grade - University

25 Qs

Quiz time

Quiz time

Assessment

Quiz

English

University

Easy

Created by

Gina Atun

Used 4+ times

FREE Resource

30 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Vendor 1 and Vendor 2 have proposed a price of IDR 500,000,000 if the equipment is delivered on the agreed

upon date. Both vendors have also proposed they receive an incentive for delivering early and absorb a penalty

for delivering late, but the amounts of incentives and penalties differ (Vendor 1=20%, Vendor 2=40%). The

probability of delivery early, on time, late for Vendor 1 (20%, 50%, 30%) and Vendor 2 (30%, 40%, 30%). Calculate the

total expected prices for Vendor 1 and 2 by totaling the expected prices if each is early, on time, and late

respectively.

Vendor 1: IDR 500M, Vendor 2: IDR 480M

Vendor 1: IDR 490M, Vendor 2: IDR 500M

Vendor 1: IDR 520M, Vendor 2: IDR 460M

Vendor 1: IDR 480M, Vendor 2: IDR 520M

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Based on Earn Value Measurement (EVM), using the cost indicators, our work considered to be on budget if

cost variance (CV)=1, cost performance index (CPI)=0

schedule variance (SV)=1, schedule performance index (SPI)=0

schedule variance (SV)=0, schedule performance index (SPI)=1

cost variance (CV)=0, cost performance index (CPI)=1

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The stakeholder management plant consist of management strategies to effectively engage stakeholders

throughout the project life cycle based on analysis of their needs, interests, and potential impact on project

success.

True

False

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In order to make the relevant information available to stakeholders, perform the report based on project

communication plan should be done by providing the status report, forecasting, and problem solving.

True

False

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In the Executing Process Group of Project Management, the overall activities should execute based on the

planning. The following planning from all the activities based on the knowledge area that should be execute,

except

Direct and Manage Project Work, Manage Communications, Perform Quality Assurance

Develop Project Team, Manage Stakeholder Engagement, Direct and Manage Project Work

Acquire Project Team, Conduct Procurement, Manage Communications

Perform Integrated Change Control, Validate

Scope, Control Risk

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The goal of Project Risk Management is to move uncertainty from threat to opportunity in the project. The risk

itself has only negative effect in overall project’s goals.

True

False

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Earn Value Measurement (EVM) variance indicator consist of cost performance index (CPI) that equal to earn

value (EV) divided by actual cost (AC) and schedule performance index (SPI) that equal to earn value (EV)

divided by planned value (PV).

True

False

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?