SBEQ2523 DELAY & EOT

SBEQ2523 DELAY & EOT

University

15 Qs

quiz-placeholder

Similar activities

Les innovations anti inondations

Les innovations anti inondations

1st Grade - University

12 Qs

Teste - Perspectiva 17-abril

Teste - Perspectiva 17-abril

University

20 Qs

Professional Practice Quiz#2

Professional Practice Quiz#2

University

10 Qs

Design 4

Design 4

University

19 Qs

Review Gambar Teknik

Review Gambar Teknik

University

12 Qs

Roof Trusses

Roof Trusses

University

12 Qs

DUBAI EXPO 2020

DUBAI EXPO 2020

University

15 Qs

aplikasi komputer teknik

aplikasi komputer teknik

University

20 Qs

SBEQ2523 DELAY & EOT

SBEQ2523 DELAY & EOT

Assessment

Quiz

Architecture

University

Practice Problem

Hard

Created by

FARRAH A

Used 5+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

1. Under PAM Contract, the contractor is required to proceed with the works:

A. As slowly as needed

B. Without any planning

C. Regularly and diligently

D. Only when instructed

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

  1. 2. What is the main clause in PAM 2006/2018 that governs Extension of Time (EOT)?

A. Clause 11.0

B. Clause 23.0

C. Clause 24.0

D. Clause 21.0

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

3. Which of the following is NOT a duty of the employer under the contract?

A. Duty of positive cooperation

B. Duty of non-hindrance

C. Duty to supply materials

D. Duty to prevent contractor from completing early

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

4. Delay caused by extreme weather is categorized as:

A. Employer delay

B. Neutral event

C. Contractor’s fault

D. Liquidated damages event

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

5. What is the consequence if the architect fails to issue an EOT certificate for employer-caused delay?

A. Contractor must pay LAD

B. Time becomes at large

C. Contractor is penalized

D. Project is terminated

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

6. Which clause requires the contractor to notify intention to claim EOT?

A. Clause 11.1

B. Clause 23.1(a)

C. Clause 23.3

D. Clause 24.0

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

7. According to Clause 23.1(b), when must the contractor submit full particulars after the delay ends?

A. Immediately

B. Within 7 days

C. Within 14 days

D. Within 28 days

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?