Project Management Quiz

Project Management Quiz

University

30 Qs

quiz-placeholder

Similar activities

Revision BQS552 2nd part

Revision BQS552 2nd part

University

25 Qs

CMT 210 Midterm Study Guide

CMT 210 Midterm Study Guide

University

35 Qs

B&V Level 3 Jeopardy

B&V Level 3 Jeopardy

University

30 Qs

ERM: LESSON 2 (ORG)

ERM: LESSON 2 (ORG)

University

35 Qs

Financial Management - Unit:1

Financial Management - Unit:1

University

25 Qs

Part 1 NSTP

Part 1 NSTP

University

32 Qs

Disaster Risk Reduction

Disaster Risk Reduction

11th Grade - University

28 Qs

Radiation Safety

Radiation Safety

University

25 Qs

Project Management Quiz

Project Management Quiz

Assessment

Quiz

Other

University

Hard

Created by

Izelle Toerien

FREE Resource

30 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the first step in traditional project management?

Monitoring

Initiation

Planning

Execution

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT a value of Agile project management?

Customer collaboration is more vital than negotiation

Working software is more important than comprehensive documentation

Strict adherence to a fixed plan

More focus on individuals and interactions than processes and tools

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why is ethical behavior important in project management?

It increases project costs

It eliminates all project risks

It elevates the standards of the profession

It reduces the need for planning

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does a Work Breakdown Structure (WBS) represent?

A list of project risks

A hierarchically structured listing of the end item

A detailed project timeline

A financial budget for the project

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a disadvantage of centralized organizations?

Decentralized decision-making

Increased employee autonomy

Limited operational responsiveness

Efficient decision-making

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of a risk register?

To outline the project budget

To list all project team members

To schedule project meetings

To record potential risks of a project in detail

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the first step in creating a risk register?

Perform a quantitative risk analysis

Perform a qualitative risk analysis

Monitor and control the risk

Create a risk response plan

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?