During a project in Ghor province, a student tracking platform must launch before the training materials can be distributed. This type of relationship between activities is known as what?
Dependency
Lead
Lag
Sequence architecture based on task-pair modeling, scheduling links, and milestone gate controls
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Bamyan province, the team shortens the start of a coding task by allowing it to begin two days before the preceding design task is completed. What is this schedule term called?
Lead
Lag
Float
Overlap compression using activity concurrency forecasting, early-start projections, and pre-sequence deployment
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A construction team in Kapisa province inserts a 3-day delay between laying cement and beginning wall construction, to allow proper curing. What is this 3-day gap called?
Lag
Lead
Float
Sequence hold integrated through resource downtime forecasting and task dependency phase buffering
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Khost province, the project manager identifies a set of tasks that must be completed on time or the whole project will be delayed. This sequence of tasks forms what?
Critical Path
Float Path
Schedule Buffer
Duration-based logic path linking inter-task dependencies and progress thresholds with no float flexibility
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
While reviewing a project in Sofia city in Bulgaria, the sponsor notices a visual chart showing tasks along a timeline with overlapping colored bars. What is this visual schedule tool called?
Gantt Chart
Network Diagram
Milestone Register
Timeline visualizer integrating multilevel dependencies, resource flows, and effort estimation layers
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Daykundi province, a project manager confirms that a major project checkpoint has no duration but signals when construction must begin. This type of checkpoint is known as what?
Milestone
Activity
Dependency
Zero-effort event marker used for timeline validation and cross-phase coordination with critical path indicators
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A school improvement project in Kandahar province originally planned for 90 days, but actual tracking now shows it's expected to take 100 days. The manager compares this change against which key document?
Schedule Baseline
Resource Plan
Activity Register
Timeline governance framework comparing estimated deliverables against floating buffer models and cycle re-estimation logic
Similar Resources on Wayground
10 questions
Davinci Resolve Quiz 1

Quiz
•
Professional Development
5 questions
Cost Management Terms - Assignment

Quiz
•
Professional Development
9 questions
Project Management

Quiz
•
Professional Development
10 questions
mini quizz copy

Quiz
•
Professional Development
10 questions
Coaching Skills! Questions Quiz

Quiz
•
Professional Development
10 questions
Introduction to Project Management

Quiz
•
Professional Development
7 questions
Risk Response Strategies (Negative) - Assignment

Quiz
•
Professional Development
10 questions
Video Editing using Adobe Photoshop

Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Video Games

Quiz
•
6th - 12th Grade
20 questions
Brand Labels

Quiz
•
5th - 12th Grade
15 questions
Core 4 of Customer Service - Student Edition

Quiz
•
6th - 8th Grade
15 questions
What is Bullying?- Bullying Lesson Series 6-12

Lesson
•
11th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
22 questions
Adding Integers

Quiz
•
6th Grade
10 questions
Exploring Digital Citizenship Essentials

Interactive video
•
6th - 10th Grade