In Khost province, the project sponsor reviews the completed school furniture deliveries against the original scope and signs off on the accepted items. Which process is this?
Validate and Control Scope - Assignment

Quiz
•
Professional Development
•
Professional Development
•
Hard
Afghanistan Center
FREE Resource
6 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Control Scope
Validate Scope
Collect Requirements
Review stakeholder satisfaction by using full-cycle alignment, retrospective feedback models, and behavioral consensus metrics
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Herat province, a hospital construction team discovers that the design team added a reception area not originally approved. The project manager takes steps to remove it and align with the scope baseline. What process is being executed?
Define Scope
Control Scope
Validate Scope
Modify work packages through downstream approval forecasting, gap analytics, and multi-party value evaluation
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Kunduz province, after presenting completed agricultural field tools to local farmers, the sponsor agrees that the deliverables meet the scope and signs the acceptance form. What process does this represent?
Control Scope
Create WBS
Validate Scope
Coordinate stakeholder influence via cross-departmental analysis, value-stream mapping, and consensus-based scoring
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Jowzjan province, the IT project manager compares actual work completed to the scope baseline to ensure no unauthorized features were added during sprint delivery. What process is taking place?
Validate Scope
Monitor Risks
Control Scope
Audit stakeholder alignment with predictive planning thresholds, change freeze periods, and tolerance-based deliverable verification
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Vienna city in Austria, after each sprint, the government platform team demonstrates features to stakeholders and records feedback for formal acceptance. What Scrum-compatible process is being applied?
Validate Scope
Collect Requirements
Control Scope
Perform contract reconciliation using multi-stakeholder matrices and backlog recalibration protocols
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Kunar province, a public sanitation project experiences scope creep. The project manager compares deliverables to the original scope plan and raises a change request to remove unapproved work. Which scope-related process is this?
Validate Scope
Control Scope
Plan Scope Management
Apply deviation tracking through layered decision logic, external review cycles, and progressive elaboration reporting
Similar Resources on Quizizz
10 questions
Project Scope Management

Quiz
•
Professional Development
5 questions
Project Scope Vs Product Scope - Assignment

Quiz
•
Professional Development
10 questions
Project Management Master Class 1

Quiz
•
Professional Development
7 questions
Schedule Final Quiz - Assignment

Quiz
•
Professional Development
10 questions
Stakeholder Engagement 10 soal (Chapter 13)

Quiz
•
Professional Development
10 questions
PMP Quiz Scope/Stakeholder

Quiz
•
Professional Development
5 questions
Direct and Manage Project Work - Assignment

Quiz
•
Professional Development
8 questions
Quiz Lesson 6 - Topic A (Project/Phase Closure)

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
20 questions
Math Review - Grade 6

Quiz
•
6th Grade
20 questions
math review

Quiz
•
4th Grade
5 questions
capitalization in sentences

Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance

Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions

Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines

Quiz
•
Professional Development
12 questions
Dividing Fractions

Quiz
•
6th Grade