
Project Procurement Management Quiz

Quiz
•
Business
•
University
•
Easy
Sas Pratama
Used 1+ times
FREE Resource
15 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Tom is a project manager for a software company. He is contracting a long-term software project with an external company. That company charges him $20/hour per employee and $300 overhead per month. What kind of contract is he using?
FP
CPAF
CR
T&M
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of the following is NOT true about bidder conferences?
All potential sellers should meet separately with the buyer.
Potential sellers should ask questions in an open forum so other sellers can hear the answers.
Bidder conferences are a good way to make sure sellers are treated fairly.
All sellers are given the same procurement documents.
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You work for a seller that is bidding on a contract. Which type of contract has the MOST risk for your company?
CPIF
T&M
FP
CPAF
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of the following BEST describes the “point of total assumption” for a contract?
The point in a cost-plus contract where the buyer assumes that the seller will need to be paid
The total cost of a T&M contract
The point in a fixed-price contract where the seller has to assume all costs going forward
The total number of resources required for a contract
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You’re trying to decide whether or not to contract out a construction job. To do it within your company, you will have to hire an engineer for $35,000 and pay a construction team $15,000 per week. A contractor quotes you a price of $19,000 per week, and your expert agrees that you won’t find a lower price than that. The job will take 16 weeks. What’s the BEST way to proceed?
Pay the contractor to do the job.
Select a T&M contract.
Don’t contract out the work; hire the engineer and pay the construction team to do the work.
Make sure the contract has a force majeure clause.
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You’re managing a project that might have to contract out work, and you’re comparing the relative advantages and disadvantages of finding a seller versus having your company do the work itself. Which process are you in?
Plan Procurement Management
Plan Contracting
Conduct Procurements
Request Seller Responses
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You’re using a qualified seller list. Which process are you in?
Plan Procurement Management
Plan Contracting
Conduct Procurements
Request Seller Responses
Create a free account and access millions of resources
Similar Resources on Wayground
12 questions
Business Law

Quiz
•
University
10 questions
DiegoVillescasACCT2301.03PRE

Quiz
•
University
10 questions
Derivative Markets Quiz

Quiz
•
University
15 questions
Business Laws - Indian Contract Act

Quiz
•
University
10 questions
INTERNAL ANALYSIS

Quiz
•
University
10 questions
CHAPTER 7 - Application of Funds

Quiz
•
University
10 questions
6 Contract enforcable

Quiz
•
University
20 questions
IBTRADE - Pre-Finals Quiz

Quiz
•
University
Popular Resources on Wayground
10 questions
Video Games

Quiz
•
6th - 12th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
10 questions
UPDATED FOREST Kindness 9-22

Lesson
•
9th - 12th Grade
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
20 questions
US Constitution Quiz

Quiz
•
11th Grade
10 questions
Exploring Digital Citizenship Essentials

Interactive video
•
6th - 10th Grade