Search Header Logo

SBEQ2523 Variation

Authored by FARRAH A

Architecture

University

Used 6+ times

SBEQ2523 Variation
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does the term 'variation' commonly refer to in construction contracts?

A breach of contract

A change to the originally agreed works

A penalty for delay

A new contract agreement

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT typically a reason for a variation?

Changes in employer requirements

Review of design

Payment delays

Statutory changes

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

According to PAM 2018, which clause defines variation?

Clause 11.0

Clause 24.0

Clause 1.1

Clause 10.3

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who is typically empowered to issue a variation under PAM 2018?

Contractor

Employer

Architect

Quantity Surveyor

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which clause ensures that variations do not vitiate the contract?

Clause 11.1

Clause 11.2

Clause 11.4

Clause 24.3

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What must accompany the notification of a variation claim under Clause 11.7(a)?

Site photographs

Verbal approval

Preliminary estimate and calculations

Copy of contract

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the deadline for submitting a notice of additional expense due to variation?

14 days

21 days

28 days

60 days

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?