Quiz 1 Training Project Management [15/04/25]

Quiz 1 Training Project Management [15/04/25]

Professional Development

5 Qs

quiz-placeholder

Similar activities

Endpoint Protection and Firewall Config

Endpoint Protection and Firewall Config

Professional Development

5 Qs

Cloud Storage Quiz

Cloud Storage Quiz

Professional Development

10 Qs

Automotive Service and Maintenance Quiz

Automotive Service and Maintenance Quiz

Professional Development

10 Qs

HTML

HTML

Professional Development

10 Qs

FMEA Day 1 of 3

FMEA Day 1 of 3

Professional Development

10 Qs

Intro to Carbon Footprint Assessment

Intro to Carbon Footprint Assessment

Professional Development

7 Qs

Quiz on Security Patches and Updates

Quiz on Security Patches and Updates

Professional Development

6 Qs

Breadboards Quiz

Breadboards Quiz

Professional Development

6 Qs

Quiz 1 Training Project Management [15/04/25]

Quiz 1 Training Project Management [15/04/25]

Assessment

Quiz

Engineering

Professional Development

Hard

Created by

Bella Fadli

Used 7+ times

FREE Resource

AI

Enhance your content

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

2 mins • 20 pts

What is the main different based on process approach between PRINCE2 and PMBOK?

PMBOK does not include process in pre-project while the PRRINCE2 does

PMBOK has initiating process group while the PRINCE2 has initiating process

PMBOK has no detail aspect of knowledge area while the PRINCE2 has

PMBOK has closed procurement process while PRINCE2 has not

2.

MULTIPLE CHOICE QUESTION

2 mins • 20 pts

In Pertamina Upstream Project, the successful project shall achieved OTOBOSOR.

What is OTOBOSOR stands for?

On Time, On Budget, On Scope, On Return

On Target, On Budget, On Scope, On Return/On Regulation

On Time, On Budget, On Scope/On Specification/On Safety, On Return/On Regulation

On Target, On Budget, On Scope/On Specification/On Safety, On Return/On Regulation

3.

MULTIPLE CHOICE QUESTION

2 mins • 20 pts

In PRINCE2, how many layer of structure in defining the boundary of the project management team?

Five (5) Layers

Two (2) Layers

Four (4) Layers

Three (3) Layers

4.

MULTIPLE CHOICE QUESTION

2 mins • 20 pts

What is the most common project organization in EPC/EPCI Contractor?

Matrix Organization

Projectized Organization

Semi-Matrix Organization

Project Team Organization

5.

MULTIPLE CHOICE QUESTION

2 mins • 20 pts

What is most common delivery method in Oil & Gas Upstream Project?

Hybrid

Agile

Iterative-Incremental

Linear-Sequential