A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully What should the project manager do next?

800-850 Updated

Quiz
•
Professional Development
•
1st Grade
•
Hard
Afghanistan Center
FREE Resource
31 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Establish the project scope and set clear team objectives
Set performance standards and direction
Hold early kick-off meetings and regular weekly meetings
Select members for their skill or potential
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project is being delayed due to a large amount of rework caused by a quality problem that is impacting the critical path. What should the project manager do?
Rebaseline the project schedule to absorb the delay.
Report the delay with rectifying actions to the project management office (PMO).
Notify the project steering committee about the cause of the delay.
Report the delay with rectifying actions to the change control board (CCB) for review,
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project is experiencing delays due to identified risks What should the project manager do to manage the project schedule?
Revise the project schedule and inform the stakeholders regarding any delays
Revise the project estimates and meet with the project team to discuss delays
Review the management reserve to identify any costs associated with the delays
Review the contingency reserve to identify any delays to the project
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A new systems project requires feedback from the accounting manager at the beginning of solution discussions and before meeting with other functional managers. The project manager knows the accounting manager will not be available until a few days before the deadline for the solution document. What should the project manager do to avoid a delay in the project?
Ask the accounting manager to delegate a team member who can support the project.
Wait for the accounting manager to be available while identifying subsequent tasks that can be compressed,
Request that the sponsor direct the accounting manager's supervisor to provide a replacement resource,
Begin discussions with other functional managers and meet with the accounting manager later.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What should an agile lead do lo ensure their team is set up for success?
Pay attention to team dynamics and understand that coaching is done simultaneously at an individual and whole-team level
Schedule sprint meetings and coaching sessions to discuss project-related information
Plan quarterly informal meetings or team bonding sessions to encourage the team to work together
Document team tasks and challenges in order to understand when to step in and help a member of the team
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is leading a project with a predictive approach for a governmental body with strictly defined requirements. In the middle of the project, the sponsor requires a significant new feature to be included. This feature was not in the original plan, nor was it part of the planning process,What should the project manager do?
Descope low-priority features that were not explicitly requested and add this feature as a high priority.
Inform the senior manager that they will need a new project management plan for this feature,
Complete the most current feature and release the resources for the new feature.
Analyze the impact of this change and present the options to the senior manager.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During protect execution the project manager observes lower velocity and a high volume of tasks m the testing queue. The project is using a hybrid approach and there are only a few sprints remaining.What should the project manager do?
Work with the team to understand and solve the issues
Provide testing training to all the project team members
Increase the sprint duration so the testing can be completed
Add a new resource with testing skills to the team
Create a free account and access millions of resources
Similar Resources on Quizizz
32 questions
651-700 Updated

Quiz
•
1st Grade
33 questions
iBPLS: BPBC Learning Assessment

Quiz
•
KG - 5th Grade
28 questions
PMI SH - Address and Remove Impediments, Obstacles, and Blockers

Quiz
•
1st - 3rd Grade
30 questions
PMI SH - Build and Lead a Team (0.5)

Quiz
•
1st Grade
30 questions
Project Management Part 1

Quiz
•
1st Grade
30 questions
Program Benefits Management

Quiz
•
1st Grade
30 questions
RESIDENTNIVERSARY

Quiz
•
1st - 3rd Grade
33 questions
Agile Training-Final Assessment

Quiz
•
1st Grade
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
20 questions
Math Review - Grade 6

Quiz
•
6th Grade
20 questions
math review

Quiz
•
4th Grade
5 questions
capitalization in sentences

Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance

Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions

Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines

Quiz
•
Professional Development
12 questions
Dividing Fractions

Quiz
•
6th Grade