
07 Test - CPM, estimating, scheduling

Quiz
•
Other
•
University
•
Medium

Jurgita Raščiuvienė
Used 2+ times
FREE Resource
25 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is not true for the critical path?
It has zero float.
It ’ s the shortest activity sequence in the network.
You can determine which tasks can start late without impacting the project end date.
It controls the project finish date.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are working on your network diagram. Activity A is a predecessor to Activity B. Activity B cannot begin until Activity A is completed. What is this telling you?
There is a mandatory dependency between Activity A and Activity B.
There is a finish - to - start dependency relationship between Activity A and Activity B.
Activity A and Activity B are both on the critical path.
Activity B is a successor to multiple tasks.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is true for float or slack time?
It ’ s calculated by adding the durations of all activities and dividing by the number of activities.
It ’ s time that you add to the project schedule to provide a buffer or contingency.
It’s the amount of time an activity can be delayed without delaying the project completion.
It is only calculated on the longest path of the network diagram.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is not a tool used to determine a project ’ s critical path?
Forward pass
Mandatory dependency
Float calculation
Backward pass
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Activity B on your network diagram has a most likely estimate of 8 days, a pessimistic estimate of 11 days, and an optimistic estimate of 6 days. What is the three - point estimate for this task rounded to the nearest whole number?
11 days
25 days
8 days
6 days
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is not true for critical path activities?
The early start is always less than the late start.
These activities are on the longest path on the network diagram.
The float is zero.
The late finish is always the same as the early finish.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are estimating a new project with team. Team members say the project is very similar to the previous one that they worked. They can list all pitfalls. Based on their experience in the previous project they can prepare the estimate very quickly. What estimation technique the team is using?
Expert judgment
Analogous estimating
PERT
Algorithmic technique function based
Create a free account and access millions of resources
Similar Resources on Wayground
20 questions
Residential Status

Quiz
•
University
20 questions
LF Library 6

Quiz
•
KG - University
21 questions
Menstrual Cycle Quiz

Quiz
•
University
21 questions
Whatever After FAIREST of ALL

Quiz
•
KG - University
23 questions
Power Rangers Dino Charge

Quiz
•
KG - Professional Dev...
20 questions
CORPORATE COGNITA round 1

Quiz
•
University
20 questions
INTRODUCTION TO INDUSTRY 4.0

Quiz
•
University
20 questions
Child development review

Quiz
•
University
Popular Resources on Wayground
10 questions
Video Games

Quiz
•
6th - 12th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
10 questions
UPDATED FOREST Kindness 9-22

Lesson
•
9th - 12th Grade
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
20 questions
US Constitution Quiz

Quiz
•
11th Grade
10 questions
Exploring Digital Citizenship Essentials

Interactive video
•
6th - 10th Grade
Discover more resources for Other
10 questions
Would you rather...

Quiz
•
KG - University
20 questions
Definite and Indefinite Articles in Spanish (Avancemos)

Quiz
•
8th Grade - University
7 questions
Force and Motion

Interactive video
•
4th Grade - University
10 questions
The Constitution, the Articles, and Federalism Crash Course US History

Interactive video
•
11th Grade - University
7 questions
Figurative Language: Idioms, Similes, and Metaphors

Interactive video
•
4th Grade - University
20 questions
Levels of Measurements

Quiz
•
11th Grade - University
16 questions
Water Modeling Activity

Lesson
•
11th Grade - University
10 questions
ACT English prep

Quiz
•
9th Grade - University