1.

MULTIPLE CHOICE QUESTION

45 sec • 20 pts

Question 1: 2 truths one Lie. Find the incorrect phrase.

  1. Microsoft Project allows you to create task dependencies like Finish-to-Start and Start-to-Finish.

  2. Microsoft Project automatically generates Gantt charts without requiring any data input.

  3. You can assign resources such as people, equipment, and materials to tasks in Microsoft Project.

A

B

C

2.

MULTIPLE CHOICE QUESTION

45 sec • 20 pts

Question 2: TWO TRUTHS ONE LIE. FIND THE INCORRECT PHRASE

  1. You can set milestones in Microsoft Project by assigning a task with a duration of zero days.

  2. Microsoft Project allows you to track actual task progress by percentage completion.

  3. Microsoft Project automatically adjusts project timelines based on delays without user intervention.

A

B

C

3.

MULTIPLE CHOICE QUESTION

45 sec • 20 pts

Question 3: Two truths one lie. Find the incorrect phrase

  1. You can assign deadlines to tasks to ensure they are completed by a specific date in Microsoft Project.

  2. Microsoft Project only supports one view of the project at a time.

  3. Task dependencies in Microsoft Project can be set to different types such as Finish-to-Start and Start-to-Start.

A

B

C

4.

MULTIPLE CHOICE QUESTION

45 sec • 20 pts

Question 4:

A) You can update a task's status by entering the percentage of completion in the "Percentage Complete" field in Microsoft Project.

B) The Gantt Chart view in Microsoft Project shows tasks, dependencies, and overall project progress visually.

c) In Microsoft Project, once a project is started, you cannot modify the task durations or start dates.

A

B

C

5.

MULTIPLE CHOICE QUESTION

45 sec • 20 pts

Question 5: two truths one lie. Find the incorrect statement

A)Microsoft Project allows you to create task dependencies to determine the order in which tasks must be completed.

B)You can track resource utilization, such as how much work a resource has completed, in Microsoft Project.

C)Microsoft Project only allows tracking of tasks, not resources.

A

B

C

6.

MULTIPLE CHOICE QUESTION

45 sec • 20 pts

QUESTION 6: two truths one lie find the incorrect statement

A) Microsoft Project allows you to print reports such as progress reports and resource allocation reports.

B) You can set up project deadlines directly in the Gantt chart view.

C) Task information, including dates and resources, cannot be modified once entered in Microsoft Project.

A

B

C

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?