IPM PG CT2

IPM PG CT2

University

34 Qs

quiz-placeholder

Similar activities

Quiz Manajemen Proyek

Quiz Manajemen Proyek

University

31 Qs

Operating System Concepts

Operating System Concepts

University

37 Qs

lSAD

lSAD

University

30 Qs

SE Quiz

SE Quiz

University

35 Qs

ITNW0613 Assessment 1

ITNW0613 Assessment 1

University

35 Qs

unit-2-requirement engineering

unit-2-requirement engineering

University

30 Qs

Project Management Quiz

Project Management Quiz

University

30 Qs

Quality & EA Framework

Quality & EA Framework

University

30 Qs

IPM PG CT2

IPM PG CT2

Assessment

Quiz

Computers

University

Easy

Created by

Rachelle Toston

Used 1+ times

FREE Resource

34 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the main goal of the Project Initiation process?

To close out completed projects

To formally select and start off projects

To create a project schedule

To measure project progress

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which document is NOT typically completed during the Project Initiation phase?

Business case

Project charter

Stakeholder identification

Work breakdown structure

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

It visually organizes project deliverables into different levels based on dependencies. It's essentially your project plan in a visual form, with your project objective at the top, then dependencies and sub-dependencies below.

Business case

Project charter

Stakeholder identification

Work breakdown structure

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

It involves identifying people, groups of people and organizations who are interested in your plan, your project or your product development.

Business case

Project charter

Stakeholder identification

Work breakdown structure

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

It is a formal short document that states a project exists and provides project managers with written authority to begin work.

Business case

Project charter

Stakeholder identification

Work breakdown structure

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of the Project Planning process?

To monitor project progress

To guide execution

To initiate new projects

To close the project

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is a key output of the Project Executing process?

Stakeholder analysis

Project scope statement

Milestone report

Project charter

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?