Project Cost Management Quiz - Topic 7
Authored by Huyền Đặng
Information Technology (IT)
University
Used 1+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
73 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Although information technology projects have a poor track record in meeting schedule goals, they have a great track record in meeting budget goals.
True
False
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Costs are often measured in monetary amounts, such as dollars, that must be paid to acquire goods and services.
True
False
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Many principles of cost management are unique to project management.
True
False
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Most executives are more concerned with profits than with other issues.
True
False
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Top management and project managers should never be concerned with the life cycle costs of projects when they make financial decisions.
True
False
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
It is much more cost-effective to spend money doing early testing on information technology projects than to wait for problems to appear after implementation.
True
False
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Labor costs are usually a small percentage of total project costs.
True
False
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?