1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A 222 percent time overrun means that a project that was planned to take one year ended up taking 1.22 years to complete
True
False
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Schedule control involves analyzing activity sequences, activity duration estimates, and resource requirements to create the project schedule
True
False
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Ideally, the project team and key stakeholders first define the project budget and then the time or schedule for the project
True
False
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The WBS is often dissected during the activity definition process as the project team members further define the activities required for performing the work
True
False
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Determining the relationships or dependencies between activities has a significant impact on developing and managing a project schedule
True
False
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Discretionary dependencies are sometimes referred to as hard logic
True
False
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Most project management software uses the precedence diagramming method
True
False
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?