1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Project is

A temporary endeavor undertaken to create a unique product, service, or result.

An artifact that is produced, is quantifiable, and can be either an end item in itself or a component item.

The person assigned by the performing organization to lead the project team that is responsible for achieving the project objectives.

An end result or consequence of a process

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The application of knowledge, skills, tools, and techniques to project activities to meet project requirements considered to be

Project Value Delivery

Project Manager

Project Team

Project Management

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The following ways are values that could create by the organizations for stakeholders, except

Enabling the changes needed to facilitate organizational transition to its desired future state

Undermining positive social or environmental contributions.

Improving efficiency, productivity, effectiveness, or responsiveness

Creating a new product, service, or result that meets the needs of customers or end users

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Activity D on a CPM network has predecessors B and C, an has successor E. D has duration 6, B’earliest finish is 18, while C’s is 20. E’s late start is 26. Which of the following is definitely true?

E is critical and has zero slack

B is a critical activity

C is completed before B

D is critical and has zero slack

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Projects exist and operate within internal and external environments that have varying degrees of influence on value delivery. Which of the following is the internal environment?

Resource availability

Industry standards

Social and cultural influences and issues

Marketplace condition

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Projects exist and operate within internal and external environments that have varying degrees of influence on value delivery. Which of the following is the external environment?

Employee capability

Academic research

Organizational culture, structure, and governance

Process assets

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The Project Management Institute Code of Ethics and Professional Conduct is based on following values that were identified as most important to the project management community.

Traceability, Respect, Adaptability, Collaborative

Profitability, Respect, Honesty, Compatibility

Responsibility, Respect, Fairness, Honesty

Honesty, Accountability, Timely Oriented, Capability

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?