Construction Management

Construction Management

University

61 Qs

quiz-placeholder

Similar activities

Actg Elec 2 - Final Exam

Actg Elec 2 - Final Exam

University

65 Qs

EE1 Unit 1

EE1 Unit 1

University

59 Qs

FPPE TEST FINAL

FPPE TEST FINAL

University

59 Qs

Exam 1 - Global Architectural History 1 - Modules 1-5

Exam 1 - Global Architectural History 1 - Modules 1-5

University

61 Qs

Topic 2: ACC466

Topic 2: ACC466

University

60 Qs

Diploma Mock November 2018

Diploma Mock November 2018

University

60 Qs

FIN 340 Practice 4 #35 - 65

FIN 340 Practice 4 #35 - 65

University

59 Qs

THC8 Midterm Examination

THC8 Midterm Examination

University

60 Qs

Construction Management

Construction Management

Assessment

Quiz

Other

University

Easy

Created by

Becca Minaker

Used 1+ times

FREE Resource

61 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of a critical path method (CPM) schedule?

To estimate project costs.

To identify the shortest possible project duration.

To manage material procurement.

To track employee attendance.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which document outlines the contractual relationship between the owner and the contractor?

Submittal log

Request for Information (RFI)

Construction contract

Meeting minutes

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does "RFIs" stand for in construction?

Required Field Inspections

Request for Information

Retained Financial Investments

Revised Foundation Installations

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a "change order" in construction?

A document approving a new subcontractor.

A modification to the original scope of work.

A request for a payment extension.

A notice of project completion.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the Earned Value Management (EVM) technique used for?

Material inventory control.

Project performance measurement.

Safety inspection scheduling.

Equipment maintenance tracking.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is a common risk mitigation strategy in construction?

Ignoring potential hazards.

Transferring risk through insurance.

Delaying project schedules.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of a punch list?

To list subcontractors’ contact information.

To document remaining minor work items.

To track daily labor hours.

To schedule project meetings.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?