Approval for the project to proceed should be undertaken by:

Project Management Quiz 3

Quiz
•
Education
•
University
•
Medium
Hooi Lim
Used 2+ times
FREE Resource
15 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The project sponsor
The project manager
The project team
The financier
Answer explanation
Approval of the project by the sponsor provides formal recognition. This is important for all size and types of projects – in particular for smaller projects whereby there may be a tendency toward simply allocating projects for implementation without any form of approval or acknowledgement by the sponsor.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A common technique used to depict the project’s scope is:
Critical path analysis
Gantt Chart
Work breakdown structure
Earned value management
Answer explanation
The most common technique is a Work Breakdown Structure (WBS) – usually hierarchical in nature. A WBS gives a visual representation of the major and sub-tasks that need to be completed.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Project management integration requires the following order of task completion:
Scoping, cost estimation and scheduling
Scoping, scheduling and cost estimating
Cost estimating, scoping and scheduling
Scheduling, scoping and cost estimating
Answer explanation
Not only should the PM elements in the planning phase be integrated (i.e relate to each other) there should be a logical order for their completion. Ideally scoping and scheduling are completed before developing the budget.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project management plan is:
A diagram that depicts the sequencing of project activities
A document that depicts a breakdown of the activities to be undertaken
A document that specifies the project requirements
A document to help guide the project during implementation
Answer explanation
The Project Management Plan (PMP) should be seen as a useful management tool for the PM to manage the project over the life. It is developed during the planning stage so that the project manager has an overview of all of the deliverables.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The critical path of a project is normally identified using:
Project requirements listing
Work breakdown structure
Cost estimate
Sequencing the activities
Answer explanation
Critical path analysis is a common project management technique that can be used to determine the optimal duration or period of time for implementation of the project. It requires consideration of the ideal sequencing of the various activities that have been identified in the WBS. Some activities may need to be undertaken before other activities can be performed.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Developing the project schedule requires:
Sequencing activities
Estimating resources
Estimating duration
All of the above
Answer explanation
The schedule requires sequencing, then estimation of resources and duration in order to then determine the project duration.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The project budget is:
The funds available to be spent
The approved estimate for the project
Funds borrowed for the project
None of the above
Answer explanation
With thorough planning, a project manager should be able to estimate the amount of money that will be needed to complete a project.
Create a free account and access millions of resources
Similar Resources on Quizizz
15 questions
Normal costing and Actual costing

Quiz
•
University
10 questions
INTRO PURCHASE & COST CONTROL

Quiz
•
University
10 questions
unit 1- Construction Materials-Introduction

Quiz
•
University
20 questions
Exam 1 - Business in Project Management

Quiz
•
University
14 questions
Project Implementation 2

Quiz
•
University
20 questions
Learning Theories for Voc. Ed.

Quiz
•
University
16 questions
Cost Estimating Theory

Quiz
•
12th Grade - University
15 questions
Project Management Network diagram Quiz (Knowledgehut.com blog)

Quiz
•
University
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
20 questions
Math Review - Grade 6

Quiz
•
6th Grade
20 questions
math review

Quiz
•
4th Grade
5 questions
capitalization in sentences

Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance

Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions

Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines

Quiz
•
Professional Development
12 questions
Dividing Fractions

Quiz
•
6th Grade