Operations Strategy

Operations Strategy

12th Grade

7 Qs

quiz-placeholder

Similar activities

sales pipeline quiz

sales pipeline quiz

KG - Professional Development

10 Qs

Marketing Planning

Marketing Planning

12th Grade

10 Qs

TR AND ALLOWANCE FOR IMPAIRMENT OF TR

TR AND ALLOWANCE FOR IMPAIRMENT OF TR

12th Grade

10 Qs

Fundamentals of Accountancy, Business, and Management 2

Fundamentals of Accountancy, Business, and Management 2

12th Grade

10 Qs

Entrepreneurship

Entrepreneurship

12th Grade

11 Qs

N5 Quality

N5 Quality

12th Grade

12 Qs

Unit 1 Business Management - Business Size and Activity

Unit 1 Business Management - Business Size and Activity

11th - 12th Grade

10 Qs

Nature and Forms of Business Organization

Nature and Forms of Business Organization

12th Grade

10 Qs

Operations Strategy

Operations Strategy

Assessment

Quiz

Business

12th Grade

Medium

Created by

Maya Kharishma

Used 2+ times

FREE Resource

AI

Enhance your content

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following statements about project management is not true?

It needs clearly defined objective

It helps to allocate resources effectively

It ensures a product has a market

It helps to control a project

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following best describes critical path analysis?

It shows how a project can be completed with maximum labour resources

It shows how a project can be completed in the minimum time

It takes account of unforeseen events

It predicts the success of a project

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

Which of the following statements is true?

E cannot start until D is completed

B cannot start until C is completed

F cannot start until D is completed

G cannot start until E and F are completed

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

Which of the following statements is true?

D is on the critical path

B is not on the critical path

E is on the critical path

F and G are on the critical path

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

How much total float does activity E have?

0 days

2 days

6 days

4 days

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

Which of the following statements about activity E is true?

It's not on the critical path

It has free float of 6 days

It has a total float of 2 days

It's on the critical path

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Total float is:

LFT - duration - EST

The total of all the free floats

The total slack in a project

The time an activity can be delayed without delaying the next activity