A major national company known for quality products has just selected a small subcontracting firm to assist with a project. The project manager from the subcontracting firm is meeting with the project team to ensure that the project is delivered according to the customer's standards.in order to ensure this, what should the project manager define and document?

900-950 UPdated

Quiz
•
Mathematics
•
1st Grade
•
Medium
Afghanistan Center
Used 2+ times
FREE Resource
32 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Quality
Estimates
Objectives
Requirements
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is managing a hybrid project that is using a contractor for a few key deliverables. The contractor has been hired to perform an important delivery, but has not yet confirmed that they can meet the required schedule.What should the project manager do?
Escalate the issue to the procurement team as the final delivery date of the project will be impacted.
Review the project scope with the stakeholders and remove the potentially delayed item from the scope.
Plan the task delivery with the contractor or vendor, highlighting the criticality of the current situation,
Check with procurement to see if there is another previously used contractor who can develop the task.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager sent the first communication about the project management plan to the team. The next day. two field engineers were asking about their roles and the project schedule. What should the project manager have done?
Confirmed that the communication was understood and solicited feedback from the team
Sent the roles and responsibilities matrix along with the project management plan
Discussed the roles with the managers to help explain them to their team members
Briefed each team member on their roles before sending the project management plan
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A bank is considering building another branch in one of three neighboring cities. The project manager has been tasked with demonstrating the benefits of building a new branch, renting an existing building, or not expanding at all.How should the project manager proceed?
Calculate the payback period (PBP) for building a new branch in each location versus renting an existing building.
Calculate the costs for each option in each location and compare the net present value (NPV) for each.
Perform a Kano analysis on building a new branch versus renting in each of the locations.
Perform a gap analysis on renting in each of the locations.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A servant leader is about to start a confidential agile research project. A high risk has been identified related to a team member disclosing details of the project with external people.What should the servant leader do to address this risk?
Include this restriction as a ground rule and ensure all team members are familiar with it by reviewing the ground rules at the end of every iteration.
Forecast the cost of the risk to calculate the required contingency reserve that needs to be allocated if the risk materializes.
Ask the functional manager to educate the team about this risk and ensure that disciplinary actions will be taken.
Contact the human resources (HR) department to ensure that disciplinary actions will be taken if the employees disclose any confidential information.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager works in a startup company and is in charge of a key project that has critical and time-sensitive delivery objectives. One of the project team members missed completing an assigned deliverable on time, despite repeated assurances from the team member that it would be completed on time.What should the project manager do next?
Record the issue then refocus the team's efforts on delivering the next set of deliverables
Give the team member a formal warning for the negative impact due to failure to deliver and not meet deadlines
Hold a team meeting to discuss team member commitments and communications
Meet with the team member and work on a development plan for them to avoid missed deliverables in the future
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In an agile project, two key stakeholders disagree about a major new requirement. Recognizing that this could lead to potential issues, what should the project manager do next?
Facilitate a meeting with the stakeholders and product owner to clarify the new need,
Update the acceptance criteria documentation to clearly reflect what was approved.
Review the new requirement and update all the stakeholders accordingly.
Ask the two key stakeholders to agree on the requirement based on a Pareto analysis.
Create a free account and access millions of resources
Similar Resources on Wayground
30 questions
BỊ BỊ

Quiz
•
1st - 5th Grade
30 questions
MATH 1 - Q1

Quiz
•
1st Grade
29 questions
Ashley present perfect australia cambridge global 4

Quiz
•
1st - 5th Grade
28 questions
Yee Kai MKT A+

Quiz
•
1st - 5th Grade
30 questions
++M3-EO2-PP3

Quiz
•
1st Grade
28 questions
Data anc beyond 2025

Quiz
•
1st Grade
30 questions
PCM2-M1

Quiz
•
1st - 5th Grade
30 questions
951-1000/ updated

Quiz
•
1st Grade
Popular Resources on Wayground
25 questions
Equations of Circles

Quiz
•
10th - 11th Grade
30 questions
Week 5 Memory Builder 1 (Multiplication and Division Facts)

Quiz
•
9th Grade
33 questions
Unit 3 Summative - Summer School: Immune System

Quiz
•
10th Grade
10 questions
Writing and Identifying Ratios Practice

Quiz
•
5th - 6th Grade
36 questions
Prime and Composite Numbers

Quiz
•
5th Grade
14 questions
Exterior and Interior angles of Polygons

Quiz
•
8th Grade
37 questions
Camp Re-cap Week 1 (no regression)

Quiz
•
9th - 12th Grade
46 questions
Biology Semester 1 Review

Quiz
•
10th Grade