A project team working in an adaptive approach is facing delays due to unforeseen risks. The project manager wants to ensure that risks are identified as early as possible and documented properly. During a risk review meeting, a team member suggests using daily stand-up meetings to capture new risks.What should the project manager do?

Project Management Scenarios

Quiz
•
Professional Development
•
4th Grade
•
Hard
Afghanistan Center
Used 1+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Use the call to verbally summarize the work status and move forward.
Use an electronic task board to give a visual representation of risks and mitigation actions.
Ask for a change in the project's budget to provide additional funding for risk resolution.
Tailor the project to use a method to make the risk identification process more formal.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During a progress meeting, the project team learns about an emerging risk that could cause major delays. The project manager realizes that the risk was not documented in the risk register. What should the project manager do next?
Ask the project sponsor to apply the management reserve to cover the impact of the risk.
Ask the project sponsor to provide additional contingency funds.
Issue a change request to modify the scope, cost, and schedule accordingly.
Use the contingency reserve and assess options for risk response.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During the execution of repair work, the root cause of the problem is found to be a defect in materials provided by the seller. The contract was fixed-price with no provisions for cost-sharing on defects. The seller refuses to cover the costs of repair, citing contract terms. What should the project manager do?
Negotiate with the contractor to cancel the repair work.
Negotiate the repair work with the contractor and explore cost-sharing options.
Proceed with the contractor without mentioning the defect.
Proceed with the contractor and subtract the additional repair cost from the seller’s payment.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In order to reduce procurement time during a bidding process, a project manager is evaluating different contracting approaches. The objective is to select a contract that ensures fairness for both the buyer and the seller. What should the project manager do?
Invite all potential bidders to a meeting.
Award the contract without negotiation.
Follow the company's bidding procedure.
Share the project objectives with all bidders.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is working on a deployment project that affects multiple departments. Some stakeholders have not been actively involved, and the project manager is concerned that their input is lacking. What should the project manager do?
Analyze the business impact in order to reprioritize the stakeholder engagement strategy.
Request to negotiate with the vendors for a lower cost solution to increase engagement.
Ask to order new equipment immediately so there are no further delays.
Acknowledge these constraints and take them into consideration when making decisions.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project team is facing communication issues with a key stakeholder who does not actively participate in meetings. The stakeholder’s input is crucial to the success of the project. What should the project manager do?
Continue to send meeting invites and assume the stakeholder will eventually join.
Schedule one-on-one discussions with the stakeholder to understand their concerns.
Escalate the issue to the sponsor and request stakeholder replacement.
Assign another team member to handle all communications with the stakeholder.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is leading an international project with stakeholders from different cultural backgrounds. Some stakeholders struggle to understand the technical jargon used in project meetings. What should the project manager do?
Continue using technical language as it is necessary for project accuracy.
Provide simplified summaries and visuals tailored to each stakeholder’s needs.
Ask the stakeholders to take additional training to understand the technical details.
Limit stakeholder involvement to only those with technical expertise.
Create a free account and access millions of resources
Similar Resources on Wayground
7 questions
Risk Response Strategies - Positive Risks

Quiz
•
4th Grade
6 questions
Risk Response Strategies - Negative Risks

Quiz
•
4th Grade
10 questions
Blank Quiz 39

Quiz
•
4th Grade
13 questions
Blank Quiz 106

Quiz
•
4th Grade
9 questions
Draft 1

Quiz
•
4th Grade
10 questions
DAP LGEMC M5S5

Quiz
•
1st - 4th Grade
10 questions
PMP 2017 PEOPLE

Quiz
•
1st - 12th Grade
7 questions
Quality Vs. Grade

Quiz
•
4th Grade
Popular Resources on Wayground
25 questions
Equations of Circles

Quiz
•
10th - 11th Grade
30 questions
Week 5 Memory Builder 1 (Multiplication and Division Facts)

Quiz
•
9th Grade
33 questions
Unit 3 Summative - Summer School: Immune System

Quiz
•
10th Grade
10 questions
Writing and Identifying Ratios Practice

Quiz
•
5th - 6th Grade
36 questions
Prime and Composite Numbers

Quiz
•
5th Grade
14 questions
Exterior and Interior angles of Polygons

Quiz
•
8th Grade
37 questions
Camp Re-cap Week 1 (no regression)

Quiz
•
9th - 12th Grade
46 questions
Biology Semester 1 Review

Quiz
•
10th Grade