1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Adam's Construction has accepted a contract to build a six-story office building. The company is using a timeline from a two-story building project the company completed in the previous month to develop the schedule for this project. Adam's Construction is using:

Analogous estimating

Parametric estimating

Three-point estimating

Reserve analysis

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which process puts more resources on the critical path?

Crashing

Fast tracking

Leading

Shortening

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The prom committee is having a contest to design the invitation and poster for this year's prom. To ensure getting the design to the printer by the January 15th deadline, the committee is holding the contest in November. This is an example of:

Analogous estimating

Parametric estimating

Three-point estimating

Reserve analysis estimating

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Craig would like to view a graphical representation of his project's work packages in a timeline bar chart format. Craig should create a:

Gantt chart

Milestone chart

Project schedule diagram

Schedule compression

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Maria determines the project duration by overestimating what she calculates by 15%. Maria is using:

Analogous estimating

Parametric estimating

Three-point estimating

Reserve analysis

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Lynn needs to finish paving his driveway before the rain arrives on Friday. He chooses to hire someone to finish the job for him because it is less expensive than getting a helper and another truck. This is an example of schedule:

Crashing

Fast tracking

Leading

Lagging

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In order to complete the finished attic remodel project on time, Brian decides to hang the ceiling fan while Petrina paints the walls. This is an example of schedule:

Crashing

Fast tracking

Leading

Lagging

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?