Unit 4 PM Review

Unit 4 PM Review

9th Grade

15 Qs

quiz-placeholder

Similar activities

PM 1 1.02 Quizizz

PM 1 1.02 Quizizz

9th - 12th Grade

15 Qs

5.00 Review Quiz

5.00 Review Quiz

9th - 12th Grade

16 Qs

2.01 Project management 1

2.01 Project management 1

9th - 12th Grade

11 Qs

RM Review Training Preparation

RM Review Training Preparation

9th Grade

16 Qs

21st Century Final Review

21st Century Final Review

9th - 12th Grade

10 Qs

Summary of the project phases

Summary of the project phases

8th Grade - University

10 Qs

Hospitality & Tourism 2.03 Review Quiz

Hospitality & Tourism 2.03 Review Quiz

9th - 12th Grade

20 Qs

BM I Unit 1.06

BM I Unit 1.06

9th Grade

20 Qs

Unit 4 PM Review

Unit 4 PM Review

Assessment

Quiz

Business

9th Grade

Medium

Created by

Brooke Burris

Used 3+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Adam's Construction has accepted a contract to build a six-story office building. The company is using a timeline from a two-story building project the company completed in the previous month to develop the schedule for this project. Adam's Construction is using:

Analogous estimating

Parametric estimating

Three-point estimating

Reserve analysis

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which process puts more resources on the critical path?

Crashing

Fast tracking

Leading

Shortening

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The prom committee is having a contest to design the invitation and poster for this year's prom. To ensure getting the design to the printer by the January 15th deadline, the committee is holding the contest in November. This is an example of:

Analogous estimating

Parametric estimating

Three-point estimating

Reserve analysis estimating

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Craig would like to view a graphical representation of his project's work packages in a timeline bar chart format. Craig should create a:

Gantt chart

Milestone chart

Project schedule diagram

Schedule compression

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Maria determines the project duration by overestimating what she calculates by 15%. Maria is using:

Analogous estimating

Parametric estimating

Three-point estimating

Reserve analysis

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Lynn needs to finish paving his driveway before the rain arrives on Friday. He chooses to hire someone to finish the job for him because it is less expensive than getting a helper and another truck. This is an example of schedule:

Crashing

Fast tracking

Leading

Lagging

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In order to complete the finished attic remodel project on time, Brian decides to hang the ceiling fan while Petrina paints the walls. This is an example of schedule:

Crashing

Fast tracking

Leading

Lagging

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?