Defects Liability Period Quiz

Defects Liability Period Quiz

12th Grade

15 Qs

quiz-placeholder

Similar activities

1.4.1 - From High School to College: Guide for Future Engineers

1.4.1 - From High School to College: Guide for Future Engineers

10th Grade - University

20 Qs

Chilean Bridge Design

Chilean Bridge Design

10th Grade - University

20 Qs

Automated Robotic Welding Quiz

Automated Robotic Welding Quiz

12th Grade

10 Qs

Engineering Skills and Safety Quiz

Engineering Skills and Safety Quiz

12th Grade

15 Qs

U9- BTEC-A.2- Lead Times in Construction Projects

U9- BTEC-A.2- Lead Times in Construction Projects

12th Grade

15 Qs

1: The function, purpose and value of standards

1: The function, purpose and value of standards

12th Grade

20 Qs

Defects Liability Period Quiz

Defects Liability Period Quiz

Assessment

Quiz

Engineering

12th Grade

Hard

Created by

Navid Mehreganian

Used 1+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the defects liability period also known as in Joint Contracts Tribunal (JCT) contracts?

Maintenance period

Rectification period

Warranty period

Inspection period

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is issued when all defects have been rectified?

Certificate of completion

Certificate of making good defects

Final payment certificate

Occupancy certificate

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What must the contractor do if defects are reported?

Ignore them

Rectify them within a reasonable time

Wait for the client’s approval

Transfer responsibility to the client

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does practical completion allow the client to do?

Terminate the contract

Occupy the site

Start new projects

Delay payments

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the statutory remedy for defects in dwellings?

Defective Premises Act 1972

Building Regulations Act 1984

Housing Act 2004

Construction Act 1996

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How long is the period for actions for breach of contract after the date of breach?

3 years

6 years

9 years

12 years

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What might trigger tenants fit out and subsequent payment of rent?

Completion of the building

Issuance of a certificate of practical completion

Rectification of all defects

Final inspection

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?