SP 2: GT Materials & Damage Mechanisms
Authored by tnbgenco. talent
English
University
Used 1+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the highest thermal efficiency of the latest Simple Cycle & Combined Cycle GT power plant?
~25% & ~30%
~30% & ~40%
~35% & ~50%
~44% & ~64%
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Name the component of the rotating section in a gas turbine which experienced highest temperature.
Combustor
Turbine
Compressors
Exhaust
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Based on the thermal cycle, name two (2) parameters that will determine the thermal efficiency of a gas turbine.
Turbine inlet temperature & exhaust temperature
Compressor pressure ratio & turbine inlet temperature
Combustor temperature & compressor inlet temperature
Compressor pressure ratio & compressor inlet temperature
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a gas turbine which components experience the highest temperature and stress?
Stage 1 turbine rotating blade
Stage 1 compressor blade
Stage 5 compressor blade
Stage 1 turbine stationary vane
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Select types of inspection interval calculations (formula) used by certain OEMs to determine the maintenance cycles.
Equivalent Operating Hours (EOH)
Factored Fired Hours (FFH) and Factored Starts (FS)
Equivalent Based Hours (EBH) and Equivalent Starts (ES)
All above
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Select the correct sequence of inspections and approximate durations to perform the work scopes on a GE Frame 6B gas turbine.
Hot Gas Path Inspection (7 days), Combustion Inspection (14 days) and Major Inspection (30 days)
Combustion Inspection (7days), Hot Gas Path Inspection (14 days) and Major Inspection (30 days)
Combustion Inspection (14 days), Hot Gas Path Inspection (7 days) and Major Inspection (30 days)
Major Inspection (14 days), Combustion Inspection (7 days) and Hot Gas Path Inspection (30 days)
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Below are among the important properties of a superalloy used in gas turbine.
High temperature strength and low oxidation resistance
High temperature strength and high oxidation resistance
High fatigue cracking resistance
a & c
b & c
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?