Waterfall mindset 2 New

Waterfall mindset 2 New

1st Grade

10 Qs

quiz-placeholder

Similar activities

Flipped Classroom Model

Flipped Classroom Model

KG - University

8 Qs

Communication Management

Communication Management

1st - 3rd Grade

10 Qs

Project Management Overview

Project Management Overview

1st - 3rd Grade

10 Qs

06. Schedule Management

06. Schedule Management

1st - 3rd Grade

12 Qs

Introduction To Jira

Introduction To Jira

1st - 3rd Grade

5 Qs

Zearn PD Session

Zearn PD Session

KG - 5th Grade

10 Qs

Hello Tech Con

Hello Tech Con

KG - 6th Grade

10 Qs

The Next Step Forward in Guided Reading Ch. 1 Review

The Next Step Forward in Guided Reading Ch. 1 Review

KG - 5th Grade

8 Qs

Waterfall mindset 2 New

Waterfall mindset 2 New

Assessment

Quiz

Professional Development

1st Grade

Easy

Created by

Afghanistan Center

Used 2+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are managing a project nearing its completion. One of your team members suggests focusing only on critical tasks to meet the final deadline. However, you notice that the project's lessons learned repository has not been updated since the project began. What should you do?

Complete the critical tasks first and address lessons learned after project closure.

Allocate time now to update lessons learned even if it impacts the schedule.

Let the project team update the lessons learned repository after the final deliverable.

Capture only key lessons and summarize them in the final project report.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During the project closure phase, you discover that a few supplier invoices are still pending payment. What is your next step?

Close the project and inform finance to handle the pending payments.

Ensure all pending invoices are paid before closing the project.

Request an exception from the sponsor to close the project.

Prioritize final deliverable acceptance over payment settlement.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project team member reports an issue during the final stages of your project. They suggest resolving it immediately without documenting it to avoid delays. What is the best action?

Resolve the issue without documentation to avoid unnecessary complexity.

Document the issue and work with the team to resolve it promptly.

Assign the issue to a task force and let them handle documentation later.

Defer the issue to the operational team post-project closure.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You have inherited a struggling project. To deliver it successfully, you must resolve conflicts between different teams and ensure alignment with the overall project goals. What should you focus on?

Act as an integrator to align team efforts and resolve conflicts.

Escalate conflicts to the project sponsor for resolution.

Prioritize technical execution over alignment activities.

Delay resolution until a formal risk review can be conducted.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Your team has completed the final deliverables, and you are in the process of closing the project. A stakeholder reminds you that some issues encountered during execution were never addressed. What should you do?

Ignore unresolved issues as the project deliverables are complete.

Ensure all issues are documented and included in the closure report.

Confirm with stakeholders that the issues are no longer relevant.

Note unresolved issues in a future risk log for other projects.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A critical supplier informs you that they cannot deliver materials for the next project phase. This impacts the project schedule and budget. How should you approach this situation?

Work to integrate the supplier’s constraints into the revised project plan.

Escalate the issue to the project sponsor immediately.

Terminate the supplier and find an alternative source.

Continue with the project plan as-is and manage risks later.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

While reviewing the project documentation during closure, you notice that the lessons learned document contains minimal input. What should you do?

Proceed with project closure and address lessons learned in the next project.

Schedule a lessons learned meeting to gather insights from the team.

Submit the document as-is to meet the deadline.

Encourage team members to submit their lessons individually post-closure.

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?