SET D - DPWH

SET D - DPWH

Professional Development

28 Qs

quiz-placeholder

Similar activities

SQL Joins Quiz

SQL Joins Quiz

Professional Development

30 Qs

13.21 CABIN SYSTEM

13.21 CABIN SYSTEM

Professional Development

31 Qs

Exploring Web Services and Spring Boot

Exploring Web Services and Spring Boot

Professional Development

25 Qs

Azure AI 900 Assignment

Azure AI 900 Assignment

Professional Development

25 Qs

Evaluasi Proses Produksi

Evaluasi Proses Produksi

Professional Development

25 Qs

Quiz tentang Internet untuk Segalanya

Quiz tentang Internet untuk Segalanya

Professional Development

25 Qs

Transportation History and Development Quiz

Transportation History and Development Quiz

Professional Development

27 Qs

14.3 exercises

14.3 exercises

Professional Development

28 Qs

SET D - DPWH

SET D - DPWH

Assessment

Quiz

Engineering

Professional Development

Easy

Created by

CHARLES TRIA

Used 1+ times

FREE Resource

AI

Enhance your content

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

28 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How many pieces of standard-size concrete hollow blocks (CHB) are required for one square meter of a CHB wall?

12

12.5

13 (correct)

13.5

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Bearing capacity tests shall be conducted at specified locations in the plans to determine:

Check pile length

Check the actual bearing capacity (correct)

Check the actual volume

NOTA

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the minimum compressive strength of concrete before tensioning the prestressing reinforcement?

22 MPa

25 MPa

28 MPa (correct)

30 MPa

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Forms for paving concrete shall remain in place undisturbed for not less than how many hours after concrete pouring?

12 hours

16 hours

24 hours (correct)

30 hours

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following statements is/are true for temporary pavement markings in road works?

III. Reflective pavement marking studs may also be used with changed markings.

a) I only

b) II only

II. Lane markings may be modified, but previous markings should be removed.

I. Temporary pavement markings may guide users through a worksite.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following statements is/are true regarding traffic controllers on road construction work areas?

a) I only

b) II only

II. Traffic controllers may control traffic while seated.

I. Traffic controllers should stand approximately 50 meters in advance of the work area.

III. Traffic controllers should be visible, clear of the traveled path, and able to view both the worksite and oncoming traffic.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In road construction, which of the following would NOT require flagmen for traffic control?

Where one lane of a two-way road or bridge is closed

Where distance to the work site is limited

Where traffic is directed through red traffic signals (correct)

Where construction machinery regularly enters or closes a road

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?