Construction Contract - Delay & EOT
Quiz
•
Construction
•
University
•
Medium
FARRAH A
Used 2+ times
FREE Resource
Enhance your content
20 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the primary responsibility of the contractor after being given possession of the site?
To renegotiate the contract terms
To commence work at their discretion
To proceed regularly and diligently to complete the work by the stipulated Completion Date
To avoid all potential disputes with the employer
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does "Employer Delay" typically refer to?
Delays caused by subcontractors
Delays resulting from the contractor's inefficiencies
Delays caused by the acts or omissions of the employer or architect
Delays due to exceptionally inclement weather
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which clause in the PAM Contract deals with the submission of notice and particulars for an extension of time (EOT)?
Clause 23.4
Clause 23.8
Clause 23.1
Clause 23.6
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
According to Clause 23.1, what must the contractor include in their notice for an EOT?
The contractor's anticipated profit margins
All subcontractor performance records
Initial estimate of EOT required, cause of the delay, and relevant particulars
The architect's anticipated completion timeline
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is classified as a "Neutral Event" under Clause 23.8?
Acts of prevention by the employer
Exceptionally inclement weather
Negligence by subcontractors
Delayed payment by the employer
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Under Clause 23.8, which event does NOT qualify for EOT?
Discovery of antiquities
Force majeure
Delays due to contractor negligence
Civil commotion
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does Clause 23.6 require the contractor to do?
Constantly use their best endeavours to prevent or reduce delay
Transfer liability for delays to the architect
Ignore delays caused by the employer
Terminate the contract in case of significant delays
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple

Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?
Similar Resources on Wayground
Popular Resources on Wayground
20 questions
Brand Labels
Quiz
•
5th - 12th Grade
10 questions
Ice Breaker Trivia: Food from Around the World
Quiz
•
3rd - 12th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
20 questions
ELA Advisory Review
Quiz
•
7th Grade
15 questions
Subtracting Integers
Quiz
•
7th Grade
22 questions
Adding Integers
Quiz
•
6th Grade
10 questions
Multiplication and Division Unknowns
Quiz
•
3rd Grade
10 questions
Exploring Digital Citizenship Essentials
Interactive video
•
6th - 10th Grade
Discover more resources for Construction
11 questions
NFL Football logos
Quiz
•
KG - Professional Dev...
20 questions
Definite and Indefinite Articles in Spanish (Avancemos)
Quiz
•
8th Grade - University
7 questions
Force and Motion
Interactive video
•
4th Grade - University
36 questions
Unit 5 Key Terms
Quiz
•
11th Grade - University
38 questions
Unit 6 Key Terms
Quiz
•
11th Grade - University
20 questions
La Hora
Quiz
•
9th Grade - University
7 questions
Cell Transport
Interactive video
•
11th Grade - University
7 questions
What Is Narrative Writing?
Interactive video
•
4th Grade - University