9. PMP_Cost

9. PMP_Cost

Professional Development

25 Qs

quiz-placeholder

Similar activities

PMP Procurement Exercise

PMP Procurement Exercise

Professional Development

20 Qs

Project Procurement Management

Project Procurement Management

Professional Development

20 Qs

Chap4. Appraisal

Chap4. Appraisal

Professional Development

24 Qs

PMP Questions 6th Edition Quiz 3

PMP Questions 6th Edition Quiz 3

Professional Development

20 Qs

Chap3. Project identification and PPP screening

Chap3. Project identification and PPP screening

Professional Development

20 Qs

Aspen Capital Cost Estimator

Aspen Capital Cost Estimator

Professional Development

23 Qs

Test Management

Test Management

Professional Development

20 Qs

Project Procurement Management 2022

Project Procurement Management 2022

Professional Development

20 Qs

9. PMP_Cost

9. PMP_Cost

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

The Do

FREE Resource

25 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The BEST description of costs that change with the amount of production is:

Variable costs

Direct costs

Fixed costs

Sunk costs

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is finalizing a project that has had repeated problems with cost conformance. He is concerned about what management will say. Which of the following types of information would be BEST for the project manager to use to evaluate performance?

The CPI

A list of complaints from senior management

The project budget

The last bar chart

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and:

Multiply by CPI

Divide by SPI

Divide by cumulative CPI

Multiply by SPI

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are in the middle of a new product development project for your publicly traded company when you discover the previous project manager made a $3,000,000 payment that was not approved in accordance with you company policies. Luckily, the project CPI is 1.2. What should you do?

Contact your manager

Ignore the payment

Put the payment in an escrow account

Bury the cost in the largest cost center available

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The main focus of life cycle costing is to:

Consider installation costs when planning the project costs

Consider operations and maintenance costs in making project decisions

Estimate installation costs

Estimate the cost of operations and maintenance

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager has run into cost difficulties. The project scope must be completed, but at less cost. The project manager should:

Evaluate benefit cost ratios

Recover some sunk cost

Perform a value analysis

Change the depreciation method for the equipment used on the project

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following BEST describes the meaning of the 50/50 rule?

Grant 50% progress on an activity when it begins and 50% upon completion

Identify 50% of risks before you start to develop responses

50% of the work is done by 50% of the people on the project

The project is given credit for completing 50% of the work when it finished

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?