Exam 2

Exam 2

Professional Development

100 Qs

quiz-placeholder

Similar activities

IoT

IoT

University - Professional Development

100 Qs

BOYMAN BAB 5 - Scouting for Boys

BOYMAN BAB 5 - Scouting for Boys

Professional Development

95 Qs

Ujian Teori Senior Avsec

Ujian Teori Senior Avsec

Professional Development

100 Qs

Coronal Polish 100 Questions

Coronal Polish 100 Questions

Professional Development

100 Qs

ข้อสอบวิชาโปรแกรมซีเอ็นซี

ข้อสอบวิชาโปรแกรมซีเอ็นซี

Professional Development

100 Qs

PK PC1250-8

PK PC1250-8

Professional Development

100 Qs

EVALUACIÓN FINAL (GRUPO 3)

EVALUACIÓN FINAL (GRUPO 3)

Professional Development

100 Qs

PAKET 100 SOAL CPNS

PAKET 100 SOAL CPNS

University - Professional Development

100 Qs

Exam 2

Exam 2

Assessment

Quiz

Professional Development

Professional Development

Practice Problem

Easy

Created by

Marc Brutas

Used 5+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

100 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

5 mins • 1 pt

Physical or mental effort work; work for which someone is paid is:

Equipment

Activity

Labor

Accomplishment

2.

MULTIPLE CHOICE QUESTION

5 mins • 1 pt

______ control category signifies that it is  1st priority activity and should be performed as needed  activity.

Limited

Variable

Unlimited

Project

3.

MULTIPLE CHOICE QUESTION

5 mins • 1 pt

The annual work quantity planned per inventory unit

Average daily production       

Crew size

Activity standard  

Quantity Standard

4.

MULTIPLE CHOICE QUESTION

5 mins • 1 pt

____ is prepared as a basis for assigning work thru verbal or written instructions

Schedule

Inspection report

Work program

Performance Budget

5.

MULTIPLE CHOICE QUESTION

5 mins • 1 pt

Which of the following Flood Control structure for protecting the river

bank from collapse by directing the flow away from the riverbank and

reduce the flow velocity near the bank?

Revetment

Dike

Spur Dike

Groundsill

6.

MULTIPLE CHOICE QUESTION

5 mins • 1 pt

Which of the following Flood Control structure designed for fixing the

riverbed and prevent it from further degradation? It is usually built

downstream of the bridge.

Revetment

Dike

Spur Dike

Groundsill

7.

MULTIPLE CHOICE QUESTION

5 mins • 1 pt

Which of the following Flood Control structure for protecting the river

bank from collapse brought about by erosion, scouring and degradation?

Revetment

Dike

Spur Dike

Groundsill

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?