CAPM Simulation Exam 1

CAPM Simulation Exam 1

38 Qs

quiz-placeholder

Similar activities

Second Semester Final

Second Semester Final

KG

41 Qs

KPS Physical Education Concepts Exam

KPS Physical Education Concepts Exam

KG - University

35 Qs

Promotion Unit Review

Promotion Unit Review

11th Grade - University

34 Qs

Entrepreneurship 1 PR6 Test Review

Entrepreneurship 1 PR6 Test Review

8th Grade

40 Qs

(Bourque) CP Pronoun Review

(Bourque) CP Pronoun Review

9th - 12th Grade

36 Qs

CAPM Simulation Exam 1

CAPM Simulation Exam 1

Assessment

Quiz

others

Hard

Created by

Putri -

FREE Resource

38 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

(1) As part of a periodic risk review, the steering committee members express concern about a significant risk that the project team missed identifying while planning the previous sprint. At the following sprint planning meeting, the project manager and team devise an appropriate, cost-effective, and realistic response plan and assign a risk owner. What else should the project manager do?
A. Implement the planned risk response
B. Record the risk, risk response, and owner in the issue log
C. Gain agreement by relevant stakeholders
D. Submit a change request to revise the risk register

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

(2) A senior executive proposes starting a project to replace a significant portion of the company’s labor force with an automated production line. Other executives express skepticism about whether this approach is the best way to boost profit margins and question whether they are prepared to sponsor such an initiative. What should be the first step in this scenario?
A. Performing a needs assessment
B. Consulting with the project management office
C. Appointing a project sponsor to create a project charter
D. Providing a project manager with the authority to apply organizational resources

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

(3) You meet with your team to determine the life cycle for your project. After analyzing the best way to define and manage requirements, develop deliverables, handle charges, control risk and cost, and engage key stakeholders, the decision is made to select a hybrid life cycle. With the project life cycle selected, how will risk and cost be controlled?
A. By adhering to the cost baseline and implementing risk responses
B. By grooming the backlog as requirements and constraints emerge
C. By increasing the cost baseline for each newly identified risk
D. By progressively elaborating the initial plans with new information

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

(4) You take over a project that has just been baselined. You review the project management plan and realize that while the development phase of the project will use an adaptive lifecycle, the development team does not have any experience with agile methodologies. The resource management plan does not specify any agile training. What should you do first?
A. Hire an agile coach to assist with the development phase of the project
B. Submit a change request to revise the project management plan
C. Change the life cycle description of the development phase to predictive
D. Adjust the roles and responsibilities in the resource management plan

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

(5) A project manager is monitoring the status of the project schedule for a product development project. The project deliverables are being produced in an iterative fashion, and the project has just completed seven of twelve planned sprints. The project manager has gathered the following information: - 17 story points were completed and accepted in the seventh sprint - 20 story points were planned for sprint #7 - One feature worth 3 story points was completed but rejected and placed back in the product backlog - The value of the features developed to date is $172,000 - Actual costs to date are $167,000 - The BAC for the project is $300,000 - The project backlog contains 250 story points - The project team has successfully completed 137 story points to date Which of the following accurately describes the schedule performance of the project for the seventh iteration?
A. The schedule variance (SV) is 0 story points, and the schedule performance index (SPI) is 1.0
B. The cost variance (CV) is $5,000, and the cost performance index (CPI) is 1.03
C. The schedule variance (SV) is -3 story points, and the schedule performance index (SPI) is 0.85
D. There is not enough information in the scenario to determine the schedule performance

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

(6) Just after the daily scrum, the project sponsor stops by the war room and introduces a new member of the organization whose role will be impacted by the project. Now that a new stakeholder has been identified, what should the agile leader do next?
A. Seek to understand the stakeholder's feelings, emotions, beliefs, and values
B. Perform stakeholder analysis by using a power/influence grid
C. Monitor the stakeholder to ensure that they have the appropriate level of engagement
D. Prioritize the stakeholder to determine the level of engagement needed going forward

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

(7) The plan for the first iteration was to complete 80 story points. However, the team was only able to complete 60. Each story point earns $1,000 for the project. The actual cost of the iteration was $70,000. As the iteration retrospective approaches, the scrum master requests that the team prepares all the data required to calculate the various earned value metrics. At the retrospective, the team determines that the cost performance index (CPI) of the iteration was _______. (On the actual exam, you will be requested to fill in the blank with the letter representing the correct answer. But here in the simulator, please select the answer below.)
A. 1.333
B. 0.750
C. 1.143
D. 0.857

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?