1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The vertical lines of PLC ladder diagram is called

Rung

Rail

branch

nest

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The horizontal lines of PLC ladder diagram is called

Rung

Rail

branch

nest

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A normally-open type contact will __________ when its bit is 0 and ________ when its bit is 1:

Open, Close

close, open

open, open

close, close

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is correct about contacts or coils seen in a Ladder Diagram PLC:

All contacts and coils are real

Contacts are real, while coils are programmed bits

Coils are real, while contacts are programmed bits

Both coils and contacts are bits in PLC memory

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When relay coil is energized it is said to be:

picked up

drop out

Roll in

none of the above

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The PLC’s can be programmed in _______

structured text

All of the above

Instruction list

ladder logic

Functional block diagram

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The instruction list plc programming language uses ________ code.

c language code

python

Mnemonic code

none of the above

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?