U9- BTEC-A.2- Lead Times in Construction Projects

U9- BTEC-A.2- Lead Times in Construction Projects

12th Grade

15 Qs

quiz-placeholder

Similar activities

Vex Block Programming

Vex Block Programming

8th Grade - University

18 Qs

Quiz on Chapter 5_Metal Alloys

Quiz on Chapter 5_Metal Alloys

12th Grade

14 Qs

Engineering Stage 6 - PPT Materials

Engineering Stage 6 - PPT Materials

12th Grade

14 Qs

Plastics Presentation Class Review

Plastics Presentation Class Review

9th - 12th Grade

20 Qs

Manufacturing Technology Quiz

Manufacturing Technology Quiz

11th Grade - University

20 Qs

Quality Management Techniques in Construction Quiz

Quality Management Techniques in Construction Quiz

12th Grade

19 Qs

Solidworks Basics Quiz for Students

Solidworks Basics Quiz for Students

10th Grade - University

20 Qs

U9- BTEC-A.2- Lead Times in Construction Projects

U9- BTEC-A.2- Lead Times in Construction Projects

Assessment

Quiz

Engineering

12th Grade

Easy

Created by

Navid Mehreganian

Used 1+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What are lead times a measure of in construction projects?

The cost of materials

The amount of time between initiating and completing a process

The number of times per week workers are on site

The quality of construction work-time

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In construction projects, what do lead times typically refer to?

The time required for the preparation of drawings

The time between placing an order and its delivery to site

The time taken to hire workers

The time needed to complete a building

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What can affect lead times besides the time taken to carry out an order?

The color of materials

Market conditions

The size of the construction site

The number of workers

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What happened to lead times for bricks, roof tiles, and lightweight blocks in September 2013?

They decreased by half

They remained the same

They more than doubled

They were unaffected

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT a variable that can affect lead times?

Strikes

Holiday periods

The color of the building

Inclement weather

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What term is used in relation to the activities of the main contractor?

Order time

Lead time

Construction time

Delivery time

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What can cause lead times to be different in other countries?

The type of construction materials

Market conditions and holiday periods

The number of workers

The size of the construction site

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?