PC12 Mock Exam

PC12 Mock Exam

12th Grade

21 Qs

quiz-placeholder

Similar activities

Module 00103 Review Questions

Module 00103 Review Questions

9th - 12th Grade

19 Qs

Floor and Wall Framing

Floor and Wall Framing

9th - 12th Grade

22 Qs

Unit 104 - End of Unit Test

Unit 104 - End of Unit Test

12th Grade

20 Qs

Carpentry 1 Orientation to the Trade

Carpentry 1 Orientation to the Trade

9th - 12th Grade

20 Qs

Health and Safety Quiz

Health and Safety Quiz

12th Grade

16 Qs

Belt and Disc Sander - Safety procedure Quiz

Belt and Disc Sander - Safety procedure Quiz

7th Grade - University

20 Qs

Construction Quiz End of Unit

Construction Quiz End of Unit

12th Grade

20 Qs

Hammers & Pry bars

Hammers & Pry bars

12th Grade

18 Qs

PC12 Mock Exam

PC12 Mock Exam

Assessment

Quiz

Construction

12th Grade

Medium

Created by

Tom Robinson

Used 1+ times

FREE Resource

21 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the process called when a project manager examines historical data to predict future project outcomes?

Trend Analysis

Data Mining

Predictive Modelling

Risk Assessment

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which method listed can be used to make progress analysis easier?
Gantt Charts
Statistical Process Control
Earned Value Analysis
Risk Matrix

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project's earned value (EV) = £1100, actual cost (AC) = £600, and planned value (PV) = £800. What is the cost variance (CV)?
£400
£500
£600
£700

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The earned value report of the project shows CPI = 1.2, PV = £500,000, SV = -£220,000. What is the cost variance of the project?
£100,000
£220,000
£300,000
£400,000

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the median of the following numbers? 13, 13, 13, 13, 14, 14, 16, 18, 21
13
14
15
16

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Assuming that the current level of progress is as planned, what can you say about the out-turn?
It will be delayed
It will be on time and within budget
There will be cost overruns
Additional resources will be required

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Complete this sentence: Planned value (PV) is also known as __________
Earned Value
Forecasted Value
Budgeted Cost of Work Scheduled
Actual Cost

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?