PC12 Mock Exam

PC12 Mock Exam

12th Grade

21 Qs

quiz-placeholder

Similar activities

Level 2 Cold Water Plumbing Exam [QUIZ 1]

Level 2 Cold Water Plumbing Exam [QUIZ 1]

12th Grade - University

20 Qs

Carpentry EOPA Part 3

Carpentry EOPA Part 3

9th - 12th Grade

19 Qs

Core Communication STUDY GUIDE

Core Communication STUDY GUIDE

12th Grade

25 Qs

Understanding Earthing Arrangements

Understanding Earthing Arrangements

12th Grade - University

20 Qs

PESTLE Analysis Quiz

PESTLE Analysis Quiz

12th Grade

23 Qs

Relationship & Management PPT 2 Quiz

Relationship & Management PPT 2 Quiz

12th Grade

26 Qs

Exploring Environmental Technology Systems

Exploring Environmental Technology Systems

12th Grade

20 Qs

JRCTC 2025 POC  FINAL EXAMS

JRCTC 2025 POC FINAL EXAMS

12th Grade

20 Qs

PC12 Mock Exam

PC12 Mock Exam

Assessment

Quiz

Construction

12th Grade

Medium

Created by

Tom Robinson

Used 1+ times

FREE Resource

21 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the process called when a project manager examines historical data to predict future project outcomes?

Trend Analysis

Data Mining

Predictive Modelling

Risk Assessment

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which method listed can be used to make progress analysis easier?
Gantt Charts
Statistical Process Control
Earned Value Analysis
Risk Matrix

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project's earned value (EV) = £1100, actual cost (AC) = £600, and planned value (PV) = £800. What is the cost variance (CV)?
£400
£500
£600
£700

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The earned value report of the project shows CPI = 1.2, PV = £500,000, SV = -£220,000. What is the cost variance of the project?
£100,000
£220,000
£300,000
£400,000

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the median of the following numbers? 13, 13, 13, 13, 14, 14, 16, 18, 21
13
14
15
16

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Assuming that the current level of progress is as planned, what can you say about the out-turn?
It will be delayed
It will be on time and within budget
There will be cost overruns
Additional resources will be required

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Complete this sentence: Planned value (PV) is also known as __________
Earned Value
Forecasted Value
Budgeted Cost of Work Scheduled
Actual Cost

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?