Building Up Rates Quiz: Reinforcement

Building Up Rates Quiz: Reinforcement

University

7 Qs

quiz-placeholder

Similar activities

Introduction Quiz

Introduction Quiz

University

10 Qs

MEACS II Fuel

MEACS II Fuel

University

7 Qs

 Quizizz2.5 prop.fisicas

Quizizz2.5 prop.fisicas

University

7 Qs

CUESTIONARIO III Y IV: TRABAJO EN ALTURA

CUESTIONARIO III Y IV: TRABAJO EN ALTURA

University

6 Qs

Pressure Basics Quiz

Pressure Basics Quiz

University

9 Qs

Lightning Quiz – Lecture 23

Lightning Quiz – Lecture 23

University

5 Qs

Kuis Gas dan Termodinamika

Kuis Gas dan Termodinamika

University

10 Qs

Quiz on Thermodynamics of Water

Quiz on Thermodynamics of Water

University

10 Qs

Building Up Rates Quiz: Reinforcement

Building Up Rates Quiz: Reinforcement

Assessment

Quiz

Engineering

University

Easy

Created by

a'fifah khairunnisa zulkiflee

Used 1+ times

FREE Resource

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the wastage percentage for cutting and damage in reinforcement work?

2%

5%

10%

15%

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the weight of a 10 mm diameter reinforcement bar per meter?

1.579 kg/m

0.888 kg/m

0.616 kg/m

0.395 kg/m

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How many hours does it take for a blacksmith to cut and bend 1 tonne of 16 mm Ø reinforcement?

30 hours

25 hours

20 hours

15 hours

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the labor output for unloading and sorting output per tonne?

2 hours

1.50 hours

2.50 hours

1 hour

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the weight of a 25 mm diameter reinforcement bar per meter?

2.466 kg/m

3.854 kg/m

6.313 kg/m

9.864 kg/m

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the labor output for placing bars in a wall for 1 tonne of 16 mm Ø reinforcement?

30 hours

35 hours

50 hours

40 hours

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the wastage percentage for ready to use bars (cut and bend)?

5%

2%

15%

10%