A project manager is managing a hybrid project. During project execution, the project manager was informed that over half of the project budget was reallocated to a project that is handling an emergency that recently occurred.What should the project manager do?

Quiz 951

Quiz
•
Professional Development
•
1st Grade
•
Easy
Afghanistan Center
Used 1+ times
FREE Resource
30 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Meet with the project sponsor to explain that the project cannot be completed as planned
Meet with the technical lead to review the sprint plan
Meet with the product owner to confirm the minimum viable product (MVP) option
Meet with the project team and reprioritize the backlog
2.
MULTIPLE SELECT QUESTION
30 sec • 1 pt
A company has undertaken a large transformation project using agile practices. The project sponsor has asked the project manager to promote the new values identified in the intended transformation to the project team.What should the project manager do?
Add a user story during sprint planning that gives recognition to behaviors that are aligned with the new values
Send a standard email to the team prior to every daily standup containing the new values
Organize a team meeting focusing on the new values associated with the transformation
Give recognition to team members' behaviors that are aligned with the new values during the sprint retrospectives
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager received the project charter for a new product. The project is expected to have two main deliveries: the hardware part that has detailed specifications already defined, including a sample machine, and the user interface software that has only a basic specification and a requirement for a user experience design approach.Which project management approach should the project manager use?
The software development has a high uncertainty level, so an agile approach is recommended for the project.
The scope is well defined; therefore, a predictive approach is straightforward and the hardware and software can by synchronized on the gates.
The deliverables are significantly different, so the project should be split into two projects that are driven by a program.
A hybrid approach will work, using agile for software development and a predictive approach for the hardware deliveries.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
After reviewing the lessons learned database, a project manager realizes that the current team may not be knowledgeable enough about organizational processes for the needs of a new project. What should the project manager do?
Develop the team members to work as a cross-functional team.
Ask a functional manager to provide the right team members.
Review the project charter to see if the scope can be modified.
Ask the portfolio manager to reassign the project to another team.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is working on a construction project. The company owner asks the project manager to provide cost estimates for the new decoration project within 4 hours.How will the project manager be able to complete this task?
Tell the owner that a rough order of magnitude will be provided.
Contact a subject matter expert (SME) for advice and consultation.
Call a meeting with the project team to identify the most appropriate approach.
Tell the owner that the task requires more time and expertise
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.In which project document should the project manager record the concern?
Request for information
Scope statement
Issue log
Risk register
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During a standup meeting, a team member raises the issue that they have blockers and impediments preventing them from moving on to the next task. How should the project lead handle this situation?
Support the team member by removing the blockers and impediments.
Allocate the blockers and impediments to the product owner to resolve.
Insist that the person who raised the blockers and impediments take ownership.
Add any blockers or impediments to the risk register,
Create a free account and access millions of resources
Similar Resources on Quizizz
30 questions
RESIDENTNIVERSARY

Quiz
•
1st - 3rd Grade
33 questions
Agile Training-Final Assessment

Quiz
•
1st Grade
26 questions
Quiz8

Quiz
•
1st Grade
25 questions
Pre-Test RPA Learning Guide Self Learning

Quiz
•
1st - 4th Grade
25 questions
The Financial Free Zone Law Quiz 3

Quiz
•
KG - Professional Dev...
33 questions
iBPLS: BPBC Learning Assessment

Quiz
•
KG - 5th Grade
28 questions
PMI SH - Address and Remove Impediments, Obstacles, and Blockers

Quiz
•
1st - 3rd Grade
32 questions
Project Management Part 3

Quiz
•
1st Grade
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
20 questions
Math Review - Grade 6

Quiz
•
6th Grade
20 questions
math review

Quiz
•
4th Grade
5 questions
capitalization in sentences

Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance

Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions

Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines

Quiz
•
Professional Development
12 questions
Dividing Fractions

Quiz
•
6th Grade