Project Management Quiz

Project Management Quiz

University

38 Qs

quiz-placeholder

Similar activities

Quantity Surveying Quiz 1

Quantity Surveying Quiz 1

University

38 Qs

Discrete Midyear Review

Discrete Midyear Review

11th Grade - University

40 Qs

QUIZZ ISTQB DE_1

QUIZZ ISTQB DE_1

3rd Grade - University

40 Qs

TCDN

TCDN

University

33 Qs

MGNF - 49

MGNF - 49

University - Professional Development

40 Qs

Rockhurst Analytics Quiz

Rockhurst Analytics Quiz

University

39 Qs

Human Resource Management Quiz

Human Resource Management Quiz

8th Grade - University

40 Qs

Making Inferences

Making Inferences

6th Grade - University

35 Qs

Project Management Quiz

Project Management Quiz

Assessment

Quiz

Mathematics

University

Hard

CCSS
HSS.MD.B.5, HSS.IC.B.3, HSS.MD.A.2

+1

Standards-aligned

Created by

Will Bynum

Used 1+ times

FREE Resource

38 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is NOT one of the fundamental steps that is included in the project control cycle?

Update technology

Develop the project plan

Establish the project benchmarks

Monitor the project performance

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is essential in an effective project control system?

Both A and B

Information

Good reporting system

None of answers are correct

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is NOT an example of a source where you might gather field information needed to develop your project controls?

Requests for information

Material invoices

Time cards

Subcontractor billing statements

Tags

CCSS.HSS.IC.B.3

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is an example of a factor that can impact project performance?

All of the answers are correct

Weather

Defective material

Overcrowded job sites

Tags

CCSS.HSS.MD.B.5

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is an escalation clause?

It is usually negotiated into the construction contract when there is suspicion that some pricing component of the estimate is in a high state of flux

It is the same thing as a contingency and tries to account for unforeseen conditions

It is a clause that covers risks associated with underground utilities, grading, and excavation

None of the answers are correct

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the riskiest element of the project control and project planning?

Estimating productivity

Cost control

Scheduling

None of the answers are correct

Tags

CCSS.HSS.MD.B.5

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does it mean to crash the schedule?

To compress the overall schedule by accelerating certain activities within it so that they finish sooner

Lengthening the overall schedule

Taking out one task

Combining tasks

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?