Project Planning and Scheduling Quiz

Project Planning and Scheduling Quiz

University

44 Qs

quiz-placeholder

Similar activities

QUIZ | Decision Analysis

QUIZ | Decision Analysis

University

40 Qs

Rockhurst Analytics Quiz

Rockhurst Analytics Quiz

University

39 Qs

Human Resource Management Quiz

Human Resource Management Quiz

8th Grade - University

40 Qs

Construction and Project Management Quiz

Construction and Project Management Quiz

University

40 Qs

CHƯƠNG 5_ Trắc nghiệm Quản trị Tài chính

CHƯƠNG 5_ Trắc nghiệm Quản trị Tài chính

University

45 Qs

Exponents and Scientific Notation

Exponents and Scientific Notation

8th Grade - University

45 Qs

Loan Fundamentals Mastery

Loan Fundamentals Mastery

12th Grade - University

41 Qs

[Algebra 2] Unit 6 Review: Statistics

[Algebra 2] Unit 6 Review: Statistics

9th Grade - University

40 Qs

Project Planning and Scheduling Quiz

Project Planning and Scheduling Quiz

Assessment

Quiz

Mathematics

University

Hard

CCSS
4.MD.A.1, HSA.CED.A.3, HSS.MD.B.5

+4

Standards-aligned

Created by

Will Bynum

Used 2+ times

FREE Resource

44 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary tool for project planning?

Schedule

Contract

Plans and specs

Cost estimate

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The two types of schedules introduced in this chapter are?

Gantt charts and network diagrams

Linear schedule and bar charts

Bar charts and fast-tracked schedules

Network diagrams and continuous activity schedules

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Gantt charts are used to:

Show overall length of the project and each activity

Show relationships between activities

Show float

Describe the work breakdown structure

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is one type of network diagram?

Activity-on-node

Activity-on-date

Activity-on-dot

Activity-on-backward pass

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT a factor when determining what type of schedule to use?

Steel or concrete structure

Size of the company

Project size

Requirements in the plans and specs

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT how schedules are used?

Conceptual schedules

Detailed schedules

Mini-schedules

Special-purpose schedules

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the typical period of time used in a short-interval schedule?

Three weeks

One day

Three months

One week

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?