1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is preparing a project closure report. The project sponsor is confident about the success of the project, but the client is not sure that the project outputs will achieve their business needs. Which aspect should the project manager highlight in the closure report to address the stakeholder's concern?
How the quality was managed
How the acceptance criteria were met
How the scope was managed
How the stakeholders were managed
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In an attempt to streamline project communications, a project manager established a shared portal for all stakeholders to get project information. The sponsor complained about this system and says that it is ineffective. What should the project manager have done to prevent this situation from occurring?
Analyzed the sponsor's communication requirements.
Confirmed that the portal is providing adequate information.
Verified that the project team is following the communications management plan.
Ensured the sponsor had the necessary skills to use the portal.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An agile project is running its fifth iteration out of 10. After the last retrospective, the team members realize that they had to work extra hours to deliver the committed work. What should the project manager do?
Ask for additional team members to maintain the velocity
Implement a checkpoint in the iteration to verify if the team is on track
Conduct a focused retrospective to help the team to discover the root cause
Ask the team to have a lower commitment for the next iteration
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A company is planning a digitization project. Which action should the project manager take first when defining the project scope?
Assess the current state process to define the scope of the digitization.
Digitize the current state process exactly as defined.
Redefine the current state process to scope the supporting software.
Develop the software that will support the current state process.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An organization in a regulated industry has decided to switch from a predictive to an agile delivery approach. It has been decided that the ongoing projects will adopt Scrum, and the project manager is still accountable for the project outcomes. During the fourth sprint demo, the customer notices that a feature is not compliant with the regulations. What should the project manager do?
Have the team consult with the compliance officer to update the definition of done (DoD) for the user stories in the past sprint.
Have the product owner consult with the change control board (CCB) to have the necessary compliance requirements implemented.
Have the scrum master organize a weekly meeting with the compliance officer, the product owner, and the project team.
Have the product owner review the user stories in the product backlog with the compliance officer on a regular basis to identify any gaps.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager has been asked to participate in the procurement process for a software application that allows customers to buy online e-learning courses. The project manager will take over the project once the supplier has been sourced. What should the project manager do before the project starts?
Ensure that the requirements for the project are understood and that the objectives are verified before approval of an agreement.
Inform the project sponsor that once the agreement has been signed, there cannot be any changes to the scope of the project.
Notify the project sponsor that the project manager cannot be involved in the agreement negotiation process.
Ask the project sponsor to involve the legal department in the negotiation for the project agreement.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A company has agreed to run a transformation project using agile approaches. During the implementation, there is pushback from the functional groups that the project is moving too fast. What should the project manager have done at the beginning of the project to prevent this from happening?
Circulated the project charter
Assessed the organizational culture
Determined the level of maturity of the employees
Communicated the project schedule
Create a free account and access millions of resources
Similar Resources on Wayground
10 questions
Agile Mindset - 1-6

Quiz
•
4th Grade
19 questions
RDL1-Test Tecniques

Quiz
•
1st - 11th Grade
15 questions
Ramp-up Mkt Cloud Admin 1x01

Quiz
•
1st - 10th Grade
17 questions
Do You Know These Shows?

Quiz
•
KG - Professional Dev...
10 questions
InEvent Quiz 17th January 2023

Quiz
•
1st - 5th Grade
12 questions
香港三項鐵人總會周年午宴 Quiz

Quiz
•
1st - 5th Grade
9 questions
Paw Patrol!

Quiz
•
KG - Professional Dev...
11 questions
Schedule Management Terms

Quiz
•
4th Grade
Popular Resources on Wayground
20 questions
Brand Labels

Quiz
•
5th - 12th Grade
10 questions
Ice Breaker Trivia: Food from Around the World

Quiz
•
3rd - 12th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
20 questions
ELA Advisory Review

Quiz
•
7th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
22 questions
Adding Integers

Quiz
•
6th Grade
10 questions
Multiplication and Division Unknowns

Quiz
•
3rd Grade
10 questions
Exploring Digital Citizenship Essentials

Interactive video
•
6th - 10th Grade
Discover more resources for Professional Development
10 questions
Ice Breaker Trivia: Food from Around the World

Quiz
•
3rd - 12th Grade
9 questions
Fact and Opinion

Quiz
•
3rd - 5th Grade
20 questions
place value

Quiz
•
4th Grade
10 questions
Order of Operations No Exponents

Quiz
•
4th - 5th Grade
20 questions
Place Value and Rounding

Quiz
•
4th Grade
12 questions
Text Structures

Quiz
•
4th Grade
15 questions
Subject-Verb Agreement

Quiz
•
4th Grade
11 questions
NFL Football logos

Quiz
•
KG - Professional Dev...