Which of the following best explains a key difference between Agile and Plan-Driven development?

Agile Software Process

Quiz
•
Information Technology (IT)
•
University
•
Medium
Shahliza Abd Halim
Used 12+ times
FREE Resource
12 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Agile focuses on comprehensive documentation, while Plan-Driven prioritizes working software.
Agile emphasizes adaptability to change, while Plan-Driven emphasizes following a strict plan.
Agile prefers sequential development, while Plan-Driven uses iterative processes.
Agile does not involve customer feedback, while Plan-Driven does.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
When is a Plan-Driven model more suitable than Agile development?
When the requirements are likely to change frequently.
When a small, co-located team is working on the project.
When the project involves high regulatory or safety requirements.
When customer feedback is critical throughout development.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What practice in Extreme Programming (XP) focuses on writing tests before writing the actual code?
Pair Programming
Test-Driven Development (TDD)
Continuous Integration
Refactoring
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In XP, what is the main benefit of Pair Programming?
It speeds up code compilation.
It encourages developers to write code faster.
It increases code quality through real-time feedback and knowledge sharing.
It reduces the need for code refactoring.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is NOT a key practice in XP?
Short release cycles
Continuous customer involvement
Prioritizing extensive documentation
Refactoring code regularly
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Scrum, who is responsible for ensuring that the team adheres to Scrum practices?
Product Owner
Development Team
Scrum Master
Project Manager
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the role of the Product Backlog in Scrum?
It contains the tasks completed by the development team.
It is a list of all items that need to be worked on, prioritized by the Product Owner.
It is used to track daily team progress.
It defines the resources required for the sprint.
Create a free account and access millions of resources
Similar Resources on Quizizz
15 questions
LIBRO 1 - CAPÍTULO XIX Gestión ágil de proyectos

Quiz
•
University
10 questions
Agile RPL

Quiz
•
University
10 questions
Review - Software Engineering

Quiz
•
University
12 questions
Basics of Scrum

Quiz
•
University
10 questions
Project Management Quiz

Quiz
•
University
14 questions
Story Points

Quiz
•
University
15 questions
Exploring Software Development and UX

Quiz
•
University
12 questions
[SE] 3. Software Process 2

Quiz
•
University
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
20 questions
Math Review - Grade 6

Quiz
•
6th Grade
20 questions
math review

Quiz
•
4th Grade
5 questions
capitalization in sentences

Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance

Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions

Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines

Quiz
•
Professional Development
12 questions
Dividing Fractions

Quiz
•
6th Grade