PC12 Week 1 - Quiz A - Variance
Authored by Tom Robinson
Construction
11th Grade
Used 2+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
13 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is a cost variance?
Difference between actual and planned costs
Difference between actual and planned schedule
Difference between actual and planned quality
Difference between actual and planned resources
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What does SPI stand for in project management?
Schedule Performance Index
Schedule Planning Index
Scope Performance Index
Scope Planning Index
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which factor can cause a cost variance?
Accurate scope definition
Correct distribution of funds
Excessive front-loading of costs
Efficient resource management
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is CPI used to measure?
Cost Performance Index
Cost Planning Index
Critical Path Index
Critical Planning Index
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which issue is an example of a schedule variance?
Performing work in the correct sequence
Accurate cost estimates
Rework due to poor quality management
Efficient use of labour
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is a false variance?
Baseline misalignment
Material price increases
Adverse weather
Labour productivity issues
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of the following can lead to a real variance?
Data entry errors
Unapproved baseline changes
Baseline misalignment
Schedule delay due to adverse weather
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?