Variations in Contractual Provisions

Variations in Contractual Provisions

University

30 Qs

quiz-placeholder

Similar activities

Risk management

Risk management

University

32 Qs

Contracts Study Questions 2

Contracts Study Questions 2

University

25 Qs

Second Half Review Ch 5, 9, 10, 13, 15 FS24

Second Half Review Ch 5, 9, 10, 13, 15 FS24

University

28 Qs

Revision

Revision

University

27 Qs

SELECTION - HRM

SELECTION - HRM

University

25 Qs

HRDM IV D Strategic Management

HRDM IV D Strategic Management

University

25 Qs

工程时间的延长

工程时间的延长

University

35 Qs

Risk Assessment - Risk Control [REVIEW]

Risk Assessment - Risk Control [REVIEW]

University

25 Qs

Variations in Contractual Provisions

Variations in Contractual Provisions

Assessment

Quiz

Other

University

Hard

Created by

Muhammad Nasrol Jamal

FREE Resource

30 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What counts as Architect’s Instruction?

The power to issue instruction comes from the contract.

Instructions must be in writing or oral.

Instructions can be confirmed by anyone.

Only the Employer can issue instructions.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What happens if the Contractor fails to comply with the Architect’s instructions within a stipulated time?

The Contractor will be penalized.

The Employer may engage others to carry out the work.

The Contractor can request more time.

The work will be delayed indefinitely.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Can the Contractor carry out variation work without prior permission or written instruction?

Yes, if he thinks it is necessary.

No, he must have a written instruction from the Architect.

Yes, if the Employer agrees.

No, unless it is an emergency.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a deemed variation?

A variation that requires no instruction.

A variation that is not authorized.

A variation that is confirmed by the Contractor.

A variation that is only verbal.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What must the Contractor do if he finds inconsistencies between statutory requirements and the Contract Documents?

Ignore them.

Notify the Architect.

Proceed with the work.

Consult with the Employer.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should the Contractor do if he encounters a conflict between the design specifications and the construction methods?

Follow the construction methods.

Consult with the Architect.

Proceed as planned.

Notify the Employer.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Is the Contractor allowed to make changes to the project scope without notifying the Architect?

Yes, if it improves the project.

No, he must inform the Architect.

Yes, if the changes are minor.

No, unless it is an urgent matter.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?