The product owner of a high-profile product is required to file weekly reports to senior management on the percentage of work completed. What should the product owner do to address this requirement?

Agile PM#3 Quiz

Quiz
•
Professional Development
•
1st Grade
•
Medium
sudiyuwono wowo
Used 3+ times
FREE Resource
25 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Establish a set of performance metrics with the project team, and provide them to senior management in a traditional format.
Include senior management in daily status meetings to ensure real-time progress updates.
Obtain agreement from senior management on reporting metrics, then update the information radiator at agreed-upon intervals.
Adjust the information radiator to senior management's traditional format and deliver weekly.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Stakeholders are concerned about the agile team's ability to release the product on time. What should the team lead do to improve this situation?
Use conflict resolution to ensure a sufficiently safe environment for healthy communication among team members.
Eliminate any remote work policies for the team until the product is delivered.
Outsource difficult portions of the backlog, avoid additional iterations, and minimize unintended team accountability.
Create an information radiator that displays updated project information in a common space.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An agile team member missed three consecutive daily standups. The scrum master learns that this team member has been spending 50 percent of their time working on a production issue for their department manager. What should the scrum master do next?
Adjust the sprint backlog's targeted story points, as their user story will unlikely be completed.
Direct the team member to stop performing non-project work.
Negotiate with their department manager to have that work occur during the next sprint.
Discuss the impact with the team, inform the product owner, and negotiate to avoid future production-issue disruptions.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An agile project is understaffed and needs additional team members to complete the deliverables. What should the project leader do when selecting new team members?
Select full-time team members who can be dedicated to the project.
Ensure team cohesion by choosing team members from the same functional areas with similar skills.
Opt for part-time team members with specialized skills.
Use team members selected by the functional managers.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Members of an extended project team are attending their first retrospective. What should the agile coach do to ensure their participation?
Ask them to sit near the front of the room.
Have them introduce themselves.
Request that they review the working agreements.
Demo the last iteration.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The project team is struggling to incorporate creativity in their solution design. Which approach could the agile coach take to foster creativity?
Provide critical feedback during retrospectives.
Encourage trial and error in a safe environment.
Guide team discussions.
Bring in outside subject matter experts (SMEs).
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What should an agile coach advise when a team wants to identify its strengths and weaknesses during recent sprints?
Keep experimenting with different methods of collecting feedback.
Compare the feedback from recent retrospectives to see if there are patterns.
Collect feedback in a safe, anonymous manner.
Recognize the team members who provide the most feedback.
Create a free account and access millions of resources
Similar Resources on Quizizz
20 questions
Domain#7 Continuous Improvement Mike Griffith

Quiz
•
1st Grade
20 questions
Domain#1 Agile Mindset & Principles Mike Griffith

Quiz
•
1st Grade
20 questions
Domain#2 Value Driven Delivery Mike Griffith

Quiz
•
1st Grade
20 questions
Domain#6 Problem Detection and Resolution Mike Griffith

Quiz
•
1st Grade
21 questions
RMP - 5. RISK RESPONSE

Quiz
•
1st Grade
23 questions
RMP - 4. RISK ANALYSIS

Quiz
•
1st Grade
20 questions
Professionalism Review

Quiz
•
KG - University
20 questions
INTERPERSONAL BEHAVIOR

Quiz
•
1st Grade
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
20 questions
Math Review - Grade 6

Quiz
•
6th Grade
20 questions
math review

Quiz
•
4th Grade
5 questions
capitalization in sentences

Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance

Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions

Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines

Quiz
•
Professional Development
12 questions
Dividing Fractions

Quiz
•
6th Grade