IS Project Management 2 - MakScie - Quiz 1

IS Project Management 2 - MakScie - Quiz 1

University

40 Qs

quiz-placeholder

Similar activities

SIA: Quiz 1 (Lesson 1-2)

SIA: Quiz 1 (Lesson 1-2)

University

40 Qs

s.e-unit-1-mcq

s.e-unit-1-mcq

University

45 Qs

PM RITA Chapter 7

PM RITA Chapter 7

University

38 Qs

Software Design Models: Waterfall and Iterative

Software Design Models: Waterfall and Iterative

8th Grade - University

44 Qs

1 Part - ERP/By @Kazima

1 Part - ERP/By @Kazima

University

37 Qs

EMPOW REVIEWER-PART 2

EMPOW REVIEWER-PART 2

University

41 Qs

INFO 242_Ch1

INFO 242_Ch1

University

40 Qs

SPP & BLDG LAWS

SPP & BLDG LAWS

University

35 Qs

IS Project Management 2 - MakScie - Quiz 1

IS Project Management 2 - MakScie - Quiz 1

Assessment

Quiz

Computers, Other, Professional Development, English

University

Easy

Created by

ALVIN CERTEZA

Used 7+ times

FREE Resource

40 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the first step in the planning phase of a project?

Budgeting

Defining the scope

Risk Management

Resource Allocation

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which tool is commonly used for task breakdown in project planning?

Gantt Chart

Pie Chart

Line Graph

Bar Chart

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What does a Work Breakdown Structure (WBS) primarily help with?

Identifying project risks

Determining the project budget

Organizing the team's workload

Breaking the project into manageable tasks

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

In project planning, what is the purpose of defining milestones?

To allocate resources

To set major goals to be achieved

To finalize the project budget

To identify potential project risks

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the significance of the critical path in project planning?

It represents the shortest path to complete the project.

It includes tasks that can be delayed without affecting the project timeline.

It represents the longest stretch of dependent tasks that determine the project duration.

It is used to allocate resources efficiently.

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following is NOT a primary objective of project planning?

Defining project scope

Identifying project risks

Enhancing team communication

Marketing the project to stakeholders

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What role does risk management play in the planning phase of a project?

It ensures that the project is completed within budget.

It identifies, analyzes, and prepares responses to project risks.

It allocates the necessary resources to each task.

It sets the project timeline.

Create a free account and access millions of resources

Create resources
Host any resource