Doug wants to ensure that his stakeholders are always referencing the most up to date project artifacts. To accomplish this, he has documented version controls and policies for project documents and artifacts. Where would Doug note this information?

Process Domain - Topic A & B

Quiz
•
Social Studies
•
Professional Development
•
Hard
Cheryl Lee
Used 2+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 10 pts
Requirements management plan
Lessons learned document
Issue log
Configuration management plan
Answer explanation
Doug should note this in the configuration management plan. The purpose of the configuration management plan is to establish policies around naming conventions and versioning control. Neither the lessons learned document, requirements management plan, nor the issue log set the standard for version control or naming conventions.
2.
MULTIPLE SELECT QUESTION
1 min • 10 pts
Ryan is a Project Manager of a Software development project that involves substantial amount of research and development.
Which development approach is most suited here?
Select the best two options.
Predictive
Iterative and Incremental
Hybrid
Agile
Answer explanation
Answer – B,D.
The Agile approach is both Iterative and incremental. It works well for projects that:
Require research and development.
Have high rates of change.
Have unclear or unknown requirements.
Have a final goal that is hard to describe.
By building a small increment and then testing and reviewing it, the team can explore uncertainty at a low cost in a short time that helps in risk reduction and maximize business value delivery.
Here, as per the situation stated in the question, options B and D are the best choices.
Agile Practice Guide - Project Management Institute Inc., 2017, Page(s) – 16.
3.
MULTIPLE CHOICE QUESTION
1 min • 10 pts
At what point in an agile project should a project manager engage stakeholders?
When challenges are encountered in the project
Throughout the project life cycle
At the end of the project
At the start of the project
Answer explanation
Project managers should actively engage stakeholders throughout the agile project lifecycle. Stakeholders should be engaged at the start and end of a project and aware of issues and challenges encountered during the project.
The other answer choices are incorrect. These options suggest that stakeholders should only be involved during a certain part of the project instead of throughout the project lifecycle.
The correct answer(s)
Throughout the project life cycle
References
2021 PMP Examination Content Outline - Domain 2 (Process), "Task 04: Engage stakeholders"
4.
MULTIPLE CHOICE QUESTION
1 min • 10 pts
The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available is termed as :-
Rolling wave planning
Progressive Elaboration
Planning package
Agile Release Planning
Answer explanation
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) -715.
5.
MULTIPLE CHOICE QUESTION
1 min • 10 pts
A new project manager joins the XGH project. He wants to review the project team directory as well as the roles and responsibilities of the team members. Which document should he review?
WBS
RACI chart
Project Team assignments
Resource Calendar
Answer explanation
Answer - C.
The Project Team assignments is a project document that records the team members and their roles and responsibilities for the project.
Choice A – WBS – Incorrect – WBS is the hierarchical decomposition of the total scope of work to be carried out by the project team. It doesn’t have information on Project Team directory.
Choice B – RACI chart – Incorrect – A RACI chart provides the level of involvement for each stakeholder associated to a task.
Choice C - Project Team assignments – Correct - The Project team assignments specify which resources are assigned to each activity. It’s a project document that records the team members and their roles and responsibilities for the project. It also can include the project team directory.
Choice D – Resource calendar – Incorrect – A resource calendar contains resource availability information for the project work. It doesn’t have information on the roles and responsibilities of the team members.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 334
6.
MULTIPLE CHOICE QUESTION
1 min • 10 pts
A project is in execution. A key stakeholder raises a change request for adding a new functionality. The Project Manager decides to do impact analysis before passing the change request to the Change Control board.
Which of the following documents would help him assess the impact of the change on the project scope?
Requirement Documentation
Risk register
Requirements Traceability Matrix
Change Management Plan
Answer explanation
The question states that the Project Manager is involved in Perform Integrated Change Control process. He or she should review the Requirements Traceability Matrix to assess the impact of the change on the project scope.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 116.
7.
MULTIPLE CHOICE QUESTION
1 min • 10 pts
Maggie is planning a release planning meeting. Which of the following is not true when it comes to hosting a release planning meeting?
Happens before the final release
All stakeholders are represented
The goal is to find which stories will be done in which iterations for the release
Defines future iterations for future releases
Answer explanation
A release planning meeting happens before each release
Create a free account and access millions of resources
Similar Resources on Quizizz
5 questions
FES OECD CIS

Quiz
•
University - Professi...
10 questions
Report and CV writing

Quiz
•
Professional Development
8 questions
Outcome Based Education

Quiz
•
University - Professi...
10 questions
Sociology of Development

Quiz
•
Professional Development
10 questions
Session 2: The Research Process

Quiz
•
University - Professi...
15 questions
W-2 CIBMM Cultural Understanding

Quiz
•
Professional Development
10 questions
S&O X DMA

Quiz
•
Professional Development
15 questions
Water resources Part 3

Quiz
•
10th Grade - Professi...
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
25 questions
SS Combined Advisory Quiz

Quiz
•
6th - 8th Grade
40 questions
Week 4 Student In Class Practice Set

Quiz
•
9th - 12th Grade
40 questions
SOL: ILE DNA Tech, Gen, Evol 2025

Quiz
•
9th - 12th Grade
20 questions
NC Universities (R2H)

Quiz
•
9th - 12th Grade
15 questions
June Review Quiz

Quiz
•
Professional Development
20 questions
Congruent and Similar Triangles

Quiz
•
8th Grade
25 questions
Triangle Inequalities

Quiz
•
10th - 12th Grade