Project Management Master Class 3

Project Management Master Class 3

Professional Development

10 Qs

quiz-placeholder

Similar activities

WT for AOII

WT for AOII

Professional Development

10 Qs

Procurement and terms related_Week1_T3

Procurement and terms related_Week1_T3

Professional Development

12 Qs

Project Management Module

Project Management Module

Professional Development

10 Qs

Project Management

Project Management

Professional Development

10 Qs

Session Risk

Session Risk

Professional Development

10 Qs

Designated Project Manager

Designated Project Manager

Professional Development

10 Qs

Quizziz 2- Knowledge Area 1 and 2

Quizziz 2- Knowledge Area 1 and 2

Professional Development

10 Qs

SG20_Test_S4_CH5 Scope

SG20_Test_S4_CH5 Scope

Professional Development

10 Qs

Project Management Master Class 3

Project Management Master Class 3

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

William Korsinah

Used 1+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is change control in project management?

The process of identifying, documenting, and controlling changes to the project deliverables.

The process of identifying, documenting, and controlling changes to the project budget.

The process of identifying, documenting, and controlling changes to the project schedule.

The process of identifying, documenting, and controlling changes to the project scope.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is resource smoothing in project management?

The process of acquiring additional resources to complete a project

The process of adjusting the project schedule to reduce resource utilization

The process of optimizing resource utilization to minimize project duration

The process of resolving resource conflicts to minimize resource utilization

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What are the types of resources that need to be managed in a project?

Human resources, technological resources, and knowledge/resources

Human resources, natural resources, and financial resources

Human resources, financial resources, and equipment/resources.

Human resources, knowledge/resources, and software/resources

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is resource management in project management?

The process of identifying and managing project stakeholders

The process of identifying, prioritizing, and managing project risks

The process of identifying, acquiring, and managing the resources required for project success

The process of identifying and tracking project progress

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a milestone in project scheduling?

A reference point for measuring progress

A point in the project schedule that marks the completion of a major deliverable

A document that lists all project activities

The final project plan

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a baseline in project scheduling?

The starting point for project planning

A document that lists all project activities

A reference point for measuring progress

The final project plan

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the critical path in project scheduling?

The path with the least amount of float in the project network diagram

The shortest path through the project network diagram

The path with the most activities in the project network diagram

The longest path through the project network diagram

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?