Contractor's Possession of Site

Contractor's Possession of Site

University

40 Qs

quiz-placeholder

Similar activities

Ontellus

Ontellus

University

41 Qs

Advance 01

Advance 01

University

40 Qs

Project Management Module 4

Project Management Module 4

University

37 Qs

CMT 210 Midterm Study Guide

CMT 210 Midterm Study Guide

University

35 Qs

kuis mikrokontroler

kuis mikrokontroler

University

40 Qs

C-207 PLC Systems 1 Pre-test

C-207 PLC Systems 1 Pre-test

University

45 Qs

Developmental language disorders in infancy and early childhood

Developmental language disorders in infancy and early childhood

University

45 Qs

ARDUINO BOARD

ARDUINO BOARD

10th Grade - University

35 Qs

Contractor's Possession of Site

Contractor's Possession of Site

Assessment

Quiz

Other

University

Hard

Created by

Muhammad Nasrol Jamal

FREE Resource

40 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the value of the performance bond as a percentage of the total Contract Sum?

5%

10%

15%

20%

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What types of insurance are required before entering the site?

Third party liability insurance

Workmen compensation

Insurance of Work

All of the above

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the duration given to the Contractor to prepare after receiving the Letter of Acceptance?

1 week

2 weeks

3 weeks

4 weeks

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In the event that the giving of the possession of the whole Site is delayed beyond ninety (90) days of the 'Date for Possession' stated in the Letter of Acceptance, what must the S.O. do?

Give written notice to the Contractor of the causes of such delay.

Allow the Contractor to claim for loss and damage.

Terminate the contract immediately.

Proceed with the works regardless of the delay.

5.

MULTIPLE SELECT QUESTION

30 sec • 1 pt

What options does the Contractor have upon receiving the written notice of delay?

Agree to proceed with the Works.

Terminate the contract.

Request for an extension of time.

Claim for loss and damage.

6.

MULTIPLE SELECT QUESTION

30 sec • 1 pt

What happens if the giving of possession of any section or part of the Site is delayed beyond ninety (90) days?

The Contractor must inform the S.O. in writing.

The Contractor can claim for any loss and/or expenses.

The S.O. must send a written notice to the Contractor.

The contract is automatically terminated.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What must the notice from the S.O. include when the possession is delayed?

Reasons for the delay.

A new date for possession.

Compensation details.

A request for the Contractor's decision.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?