1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

If you are leading a project where requirements are not well defined, change is expected, and the customer wants several deliveries of useful products, which development approach might not be appropriate to use?

predictive

incremental

iterative

adaptive

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In which of the five project management process groups are activities performed that relate to each knowledge area?

initiating

planning

executing

closing

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What document provides justification for investing in a project?

project charter

business case

net present value analysis

benefits management plan

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What document formally recognizes the existence of a project and provides direction on the project’s objectives and management?

project charter

business case

stakeholder register

benefits management plan

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A _____________ is an emergent, ordered list of what is needed to improve the product. It is the single source of work undertaken by the Scrum team.

product backlog

Scrum backlog

product work breakdown structure

product roadmap 

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?