PMP Foundation

Quiz
•
Other
•
Professional Development
•
Hard
Tạ Nguyệt
FREE Resource
15 questions
Show all answers
1.
MULTIPLE SELECT QUESTION
1 min • 1 pt
In iteration-based Agile, what questions will the team pose during daily stand-ups? (Select
three.)
What did I complete since the last stand-up?
What will I complete between now and the next stand-up?
What do we need to finish as a team?
What are my impediments?
2.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
What is the role of a servant leader?
To ensure the team delivers planned outcomes of the project
To charter the team and monitor adherence to agreements
To facilitate the Agile events, including daily stand-up
To facilitate the team’s discovery and definition of Agile
3.
MULTIPLE SELECT QUESTION
1 min • 1 pt
Which of the following are events used by Scrum teams? (Select three.)
Sprint planning
Weekly scrum
Sprint review
Sprint retrospective
4.
MULTIPLE SELECT QUESTION
1 min • 1 pt
Which of the following statements are true? (Select three.)
Risk management is a proactive practice within project management.
Risks are prioritized during qualitative risk analysis.
Watch lists contain near-term risks that must be monitored carefully.
Risk symptoms are considered when evaluating if a risk is a near-term risk.
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project manager of ABC company. is in the process of assigning resources to
her current project. At the end of the day, she receives an angry call from the director
of engineering, who is upset that his senior systems administrator was assigned to the
project without his consent. At this stage, what should the project manager do to keep this
resource?
Negotiate with the director for the resource
Agree by phone but keep the resource
Get the project sponsor involved
Call the CEO, who is a personal friend
6.
MULTIPLE SELECT QUESTION
1 min • 1 pt
When should Agile teams hold retrospectives? (more than 1)
At the start of the project
When the team feels stuck
When a major milestone is reached
At the conclusion of an iteration or increment
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Sally, a member of the project management team, walks into a room where two project
team members are seen arguing over the schedule. One team member feels that an
additional resource is needed to meet an upcoming deadline, while another feels that the
risk is not as high and that the schedule should be left alone. Sally takes a moment to
review the schedule and instructs the team members to leave it. What type of resolution
technique did Sally use?
Collaborating
Smoothing
Withdrawing
Forcing
Create a free account and access millions of resources
Similar Resources on Wayground
14 questions
E6F Unit 9 - Corporate Citizenship

Quiz
•
Professional Development
15 questions
Introduction to Project Management for Nestle Management Trainee

Quiz
•
Professional Development
10 questions
ITIL 4 Foundation Practice (3)

Quiz
•
Professional Development
15 questions
Super Bowl Trivia

Quiz
•
Professional Development
10 questions
BFDI/BFB/TPOT quiz

Quiz
•
Professional Development
15 questions
Atoha PMP lesson2

Quiz
•
Professional Development
10 questions
Lesson 4: SD Methodologies. Discussing Waterfall, Agile & Scrum

Quiz
•
Professional Development
10 questions
5 - Exploring LPM

Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Video Games

Quiz
•
6th - 12th Grade
20 questions
Brand Labels

Quiz
•
5th - 12th Grade
15 questions
Core 4 of Customer Service - Student Edition

Quiz
•
6th - 8th Grade
15 questions
What is Bullying?- Bullying Lesson Series 6-12

Lesson
•
11th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
22 questions
Adding Integers

Quiz
•
6th Grade
10 questions
Exploring Digital Citizenship Essentials

Interactive video
•
6th - 10th Grade